  Toutes les notes concernant les Commissionning de ThomX, Page 48 of 63  Not logged in ThomX    logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Statusdown Type Category Important Subject Icon Text Attachments
  Draft   Mon Oct 25 19:23:51 2021 Entered by Super Team from 134.158.195.142 on Mon Oct 25 19:23:35 2021    , entered from 134.158.195.142 Passage de la sect   
  121   Tue Oct 26 15:19:17 2021 Entered by Moutardier Alexandre from 134.158.195.144 on Tue Oct 26 15:18:59 2021 InfoRF D1 Image PIC PBC photodiode a l'oscilloscope en salle de controle Attenuateur RF canon : 0.25 dB

Orange : Photodiode
Vert : PBC
 image_PIC_PBC_photodiode.png 
  154   Mon Nov 8 12:16:13 2021 Entered by sophie chance from 134.158.195.141 on Mon Nov 8 12:15:59 2021 LinacLaser energie laser Mesure de 12 uJ avant hublot   
  157   Mon Nov 8 18:01:06 2021 Entered by Moutardier Alexandre from 134.158.195.144 on Mon Nov 8 18:00:52 2021 InfoDiag | Linac Commissionning Scan charge phase Scan charge ICT linac phase canon fait
le 08 Nov 2021
 scan_charge_phase_08-11-2021.png 
  159   Tue Nov 9 11:25:33 2021 Entered by sophie chance from 134.158.195.141 on Tue Nov 9 11:25:18 2021 InfoLinac Commissionning Faisceau et scan charge phase Faisceau jusqu'à sortie section
reproductible depuis hier, pas de steerer
observation sur caméra sortie section
 2021-11-9_11_24_24_scan_charge_phase.jpg 
  172   Fri Nov 19 09:24:41 2021 Entered by Moutardier Alexandre from 134.158.195.144 on Fri Nov 19 09:24:11 2021 UrgentInfra Trou dangereux !!! Ce matin en verifiant les orientations
des jauges dans l'anneau pour faire des
simulations correcte j'ai du entrer dans
 trou_escalier_anneau.jpg 
  197   Thu Dec 2 10:38:44 2021 Entered by Maher OMEICH from 134.158.91.212 on Thu Dec 2 10:38:07 2021 AnneauAimants intervention Soleil Bonjour, Patrick Alexandre et Didier Muller
( Soleil ) viendrons demain Vendredi 03/12
toute l'après midi, j'aurai
  
  221   Thu Dec 16 10:40:03 2021 Entered by Moutardier Alexandre from 91.168.92.148 on Thu Dec 16 10:39:49 2021 InfoCC test en ssh Connection ssh sur client4 pour tester
une modification de health_check
  
  222   Thu Dec 16 14:57:31 2021 Entered by Moutardier Alexandre from 91.168.92.148 on Thu Dec 16 10:39:49 2021 InfoCC RE: test en ssh Modifications faites, testées et
fonctionnelles.

  
  223   Thu Dec 16 14:58:50 2021 Entered by Moutardier Alexandre from 91.168.92.148 on Thu Dec 16 14:58:26 2021 ProblemAimants | Linac Commissionning Alimentation en état FAULT !!! D'après health_check toutes
les alimentations electrique des solenoides,
deviateur et quadrupole sont en état
  
  237   Mon Jan 10 09:27:14 2022 Entered by Moutardier Alexandre from 193.55.29.170 on Mon Jan 10 09:26:50 2022 FixDiag | CC | Linac Commissionning Automatique "health check" Allumage de client 5. Pourquoi était-il
éteint sachant qu'il y a des ds
qui doivent tourner dessus ?
  
  254   Fri Jan 14 14:42:14 2022 Entered by Super Team from 134.158.195.142 on Fri Jan 14 14:41:42 2022 InfoDiag Comparaison signaux WAC Signal ICT linac : 


2022-01-14_ictLI-new_delay.png


 

Avant modification du delay de
 2022-01-14_FC-new_delay.png2022-01-14_ictLI-new_delay.png2022-01-14_ictTL1-new_delay.png2022-01-14_FC-old_delay.png2022-01-14_ictTL1-old_delay.png 
  255   Fri Jan 14 15:03:02 2022 Entered by Super Team from 134.158.195.142 on Fri Jan 14 15:02:49 2022 InfoLaser | Linac Commissionning Ouverture iris laser Ouverture de l'iris laser PC au
maximum => augmentation de la charge a
65 pC +- 1.2pC
 2022-01-14_mesure_charge.png 
  256   Fri Jan 14 15:44:53 2022 Entered by Alexandre Moutardier from 134.158.195.142 on Fri Jan 14 15:44:40 2022 InfoDiag | Linac Commissionning Premier faisceau OTR ! Première lumière OTR
pris sur la station TL/DG/SST.01 !

Images are without and with background
 2022-01-14_15_42_03_tl_dg_sst_01-ccd_01_first_otr_light_kane_panchal_log_scale_True_despeckle_False_min_scale_0_max_scale_100.png2022-01-14_15_46_00_tl_dg_sst_01-ccd_01_first_otr_light_kane_panchal_with__bkg_subtraction_log_scale_True_despeckle_False_min_scale_0_max_scale_100.png 
  261   Mon Jan 17 10:30:21 2022 Entered by Alexandre Moutardier from 134.158.195.141 on Mon Jan 17 10:30:07 2022 InfoElectronique   État de la machine :

Laser : OFF -> normal
RF : RedPitaya a redémarrer
 2022-01-17_10-28-14_health_check.png 
  Draft   Tue Jan 18 11:57:15 2022 Entered by Hayg Guler from 134.158.91.29 on Tue Jan 18 11:44:00 2022    , entered from 134.158.91.29    image_SST2021-11-23_19_35_07_tl_dg_sst_01-ccd_01_RAW_2.png 
  267   Thu Jan 20 11:24:49 2022 CB/HG/SC/HM ProblemLinac Commissionning modulateur interlock  Interlock modulateur empechant de passer
en HV 

sur le modulateur c'est le
 Screenshot_from_2022-01-20_11-26-29.png 
  301   Mon Feb 7 18:19:49 2022 Entered by Maher OMEICH from 78.193.58.208 on Mon Feb 7 18:19:11 2022 InfoRF D1 modulateur Début de l'intervention de Scandinova
sur le modulateur ce matin

modification dans le soft du modulateur,
  
  302   Tue Feb 8 08:54:53 2022 Entered by Super Team from 134.158.195.141 on Tue Feb 8 08:54:38 2022 UrgentLinac Commissionning   Bonjour Hayg,

L'IHM RF GUN_Section ne s'ouvre
pas merci pour la débloquer
  
  303   Tue Feb 8 09:03:44 2022 Entered by Super Team from 134.158.195.141 on Tue Feb 8 08:54:38 2022 UrgentLinac Commissionning RE:  Faut redémarrer les Redpitaya en
hard.

 
  