ID Date Author Status Type Category Important Subjectdown Icon Text Attachments
  666   Thu Jan 12 08:55:33 2023 SC/ND/IC/VK/VM AnneauRing Commissioning Faisceau  Mise en chauffe modulateur et refroidissements

Résistivité : 3.53
MOhm et Pression eau : 3.7
 11x 
  337   Tue Feb 15 15:50:00 2022 Entered by Super Team from 134.158.195.141 on Tue Feb 15 15:49:46 2022FixedLinacLinac Commissionning Faisceau ATK panel des wavecatchers bloqué.
Intervention de Philippe.

Re-démarrage dans Astor
  
  372   Thu Feb 24 13:37:08 2022 Entered by JNC/SC/CB from 134.158.195.142 on Thu Feb 24 13:36:53 2022 LinacLinac Commissionning Faisceau Energie laser = 27 uJ sur la cathode

IHM Camera laser s'est gelé,
impossible de le rouvrir et de voir l'image
 message_alerte_laser.png 
  405   Thu Mar 17 17:54:29 2022 Entered by JNC/HG/AM/SC from 134.158.195.143 on Thu Mar 17 17:54:14 2022Under ProcessLinacLinac Commissionning Faisceau MeanStd fonctionne

Cyclage des dipoles Q01 Q02 et
Q03 fait
  
  444   Thu Apr 14 16:31:58 2022 Entered by SC/ND from 134.158.195.141 on Thu Apr 14 16:31:44 2022Under ProcessLinacLinac Commissionning Faisceau Phase 145 degres charge max Q = 77 pC

HT = 1090 V

Energie max (-40 degres) Q = 69
  
  492   Tue Jul 5 10:26:33 2022 Entered by Super Team from 134.158.195.141 on Tue Jul 5 10:26:17 2022Under ProcessLinacLinac Commissionning Faisceau 10h20 Mise en chauffe modulateur et chillers
(MO, SC)

Arret modulateur pour changement
  
  273   Thu Jan 20 18:17:56 2022 Entered by Super Team from 134.158.195.141 on Thu Jan 20 18:17:38 2022FixedInfoLinac Commissionning FIn de shift 18h20 : fin de shift

Redpitaya relancés vers
18h en redémarrant en hard 
 charge_phase__at_20-01-2022__18-16-59.jpgcharge_phase__at_20-01-2022__18-06-40.jpg 
  1203   Thu Mar 5 13:19:22 2026 MJ VM DN RC HG Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Etudes matching icon1.gif Mesures : Spectres et taille source
X + Quads scans associées, @
  
  1212   Sun Mar 15 18:42:53 2026 MJ HG VKFixedShift summaryLinac Commissionning | Ring Commissioning Etudes de points MATCHING - 13 mars 2026 Programme :
Etudes points Matching
==============================
  
  948   Tue Oct 29 10:31:45 2024 HG, SCUnder ProcessInfoLinac Commissionning Etude faisceau linac 9h30 : Mise en chauffe

10h31 : mise en route faisceau

On se place à 0 dB,
 Soleno_Align_noCol1.png 
  961   Thu Nov 14 09:21:51 2024 Entered by Viktor Soskov from 134.158.195.153 on Thu Nov 14 09:21:36 2024FixedInfoLaser Etat laser Bonjour, rien n'a change au faisceau
laser (distribution reste le meme,l'energie
sur la cathode =60mkJ, Iris = 1.3mm, Att
  
  1036   Thu Mar 13 11:25:29 2025 Entered by Viktor Soskov from 134.158.195.153 on Thu Mar 13 11:25:13 2025FixedLinacLaser Etat laser Bonjour, le parcours optique a ete realigne.

L'enegie UV sur la cathode
= 48uJ , Iris = 1.3mm, Att = 410
  
  1037   Thu Mar 13 11:57:19 2025 Entered by Viktor Soskov from 134.158.195.153 on Thu Mar 13 11:57:03 2025FixedInfoLaser Etat laser Voici les distibutions UV laser sur lacathode
avant et apres l'alignement
 Avant.pngApres.png 
  151   Mon Nov 8 09:21:48 2021 Entered by sophie chance from 134.158.195.141 on Mon Nov 8 09:21:32 2021Under ProcessInfoDiag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning Etat des lieux  SC et AM

Fermeture des sous-sols et de la
crinoline
  
  472   Tue Jun 7 09:53:01 2022 Entered by ND/JNC/VC/VS/MO/SC from 134.158.195.141 on Tue Jun 7 09:52:47 2022Under ProcessLinacLinac Commissionning Etat des lieux Presents: SC, ND, JNC, VS, MO

Fermeture casemate

Tests des DSs en cours
  
  720   Mon Mar 27 13:55:41 2023 Entered by Super Team from 134.158.195.141 on Mon Mar 27 13:55:24 2023Under ProcessInfoLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Etat ThomX  Cavité FP a terminé son intervention

Mise sous vide possible cette après-midi

14h Intervention IHM cavité
  
  804   Tue Oct 10 13:47:16 2023 MJ KD Shift summaryLinac Commissionning | Ring Commissioning Essai de validation synchro electron / laserFPC ** 500.25 MHz anneau

** laser locke tres instable

** Vers 13h : IP retrouvee
 2023-10-10_14-21-43.png2023-10-10_17-38-46.png 
  148   Fri Oct 29 15:58:58 2021 Entered by Super Team from 134.158.195.142 on Fri Oct 29 15:58:45 2021Not FixedLinacLinac Commissionning Erreur DS CALC sur terminal Message apparu dans un terminal après
avoir lancé ipython create_DS_Att_Deph_write.py


Le moteur sur l'IHM
  
  Draft   Fri Oct 29 15:56:01 2021 Entered by Super Team from 134.158.195.142 on Fri Oct 29 15:55:48 2021Under ProcessQuestion  Erreur DS CALC 

 

alexandre.moutardier@client3:~/git/panneaux/PlateformeIHMThomX$
  
  171   Thu Nov 18 18:39:18 2021 Entered by Hayg Guler from 134.158.195.141 on Thu Nov 18 18:39:04 2021Under ProcessShift summaryLinac Commissionning Energies avant section pour différents gradients  Methode : 

on utilise le steerer LI/PS/STR01-V01
et les mesures sont faites sur le Yag de
  