560
|
Wed Sep 21 20:07:01 2022 |
Entered by Marie Jacquet from 134.158.89.45 on Wed Sep 21 20:06:44 2022 | | Shift summary | Linac Commissionning |
|
BPM LINAC + TL : dispersion tir a tir ? | | Aujourd'hui Iriya m'a montre en
salle de controle une "etendue"
de ~4mm de l'orbite du faisceau mesuree |
|
|
Draft
|
Wed Sep 21 09:28:54 2022 |
VC | Under Process | Shift summary | Ring | Linac Commissionning |
|
Shift du jour | | Demarrage modulateur et refroidissement
9h30.
Pb alim quad anneau (Ri-C2-QP6) |
|
|
558
|
Tue Sep 20 14:32:09 2022 |
SC VC | Under Process | Shift summary | Linac Commissionning |
|
Commissonning Linac | | 13H demarage modulateur
14H cyclage aimant (4 quads de
l'anneau ne cycle pas + EL PS DP (acces |
|
|
557
|
Mon Sep 19 11:15:51 2022 |
Entered by Super Team from 134.158.195.141 on Mon Sep 19 11:15:38 2022 | Under Process | Linac | LI |
|
Démarrage technique | | Démarrage modulateur et chillers
(MO)
Problème avec les icepap |
|
|
556
|
Fri Sep 16 16:39:55 2022 |
Entered by Marie Jacquet from 134.158.205.33 on Fri Sep 16 16:39:35 2022 | | Shift summary | Linac Commissionning |
|
shifts des 12 et 13 septembre - axes MAG vs BPM_TL et YAG_TL | | Données prises les 12 et
13 septembre
Très faible charge (<10 |
|
|
555
|
Fri Sep 16 16:27:49 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 16 16:27:35 2022 | Fixed | Info | Linac Commissionning |
|
Laser status | | Bonjour, voici l"énergie sur
la cathode (µJ) en fonction du diamètre
de l'iris (mm) |
|
|
Draft
|
Fri Sep 16 16:13:55 2022 |
Entered by Marie Jacquet from 134.158.205.33 on Fri Sep 16 16:13:31 2022 | | Shift summary | Linac Commissionning |
|
| | |
|
|
553
|
Fri Sep 16 13:39:24 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 16 13:39:08 2022 | Fixed | Info | Linac Commissionning |
|
Laser status | | Bonjour, j'ai changé 2 miroirs
du parcous optique (2 moroirs du periscope
dans la salle laser). La distribution est |
|
|
552
|
Fri Sep 16 10:11:24 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 16 09:12:19 2022 | Fixed | Urgent | Linac Commissionning |
|
RE: RE: RE: Shutters Laser | | Problème shutter résolu
|
|
|
551
|
Fri Sep 16 10:10:36 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 16 09:12:19 2022 | Fixed | Urgent | Linac Commissionning |
|
RE: RE: Shutters Laser | | Shutter casemate ouvert
Shutter salle laser encore fermé
|
|
|
Draft
|
Fri Sep 16 10:09:15 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 16 09:12:19 2022 | Fixed | Urgent | Linac Commissionning |
|
RE: Shutters Laser | |
Entered |
|
|
549
|
Fri Sep 16 09:12:35 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 16 09:12:19 2022 | Fixed | Urgent | Linac Commissionning |
|
Shutters Laser | | Bonjour,
je n'arrive pas ouvrir les
shutters dans la salle laser et dans la casemate, |
|
|
548
|
Thu Sep 15 09:34:23 2022 |
MO | Fixed | Other | Linac Commissionning |
|
balise T3G | | La balise T3G était en défaut
ce matin, redémarrage du PC ( LB 9000
coté THOMX ) pour corriger |
|
|
547
|
Wed Sep 14 23:06:40 2022 |
ND, AM, VC, ML, SC | Under Process | Shift summary | Diag | Ring Commissioning |
|
Programme faisceau 15/9 | | 15-09-2022:
Marie Labat, VC, ND, AM
9h30 Mise en chauffe modulateur |
|
|
546
|
Wed Sep 14 15:18:17 2022 |
CB/KD/HG | Under Process | Info | Linac Commissionning |
|
Shift Linac + TL | | Phase Qmax : 368°
Alignement / centre QP3( QP1 et
QP2 éteints) --> LI : STR1H : -1.62, |
   |
|
545
|
Tue Sep 13 11:49:50 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Tue Sep 13 11:49:29 2022 | Fixed | Info | Linac Commissionning |
|
Phase Stability | | Bonjour, voici la stabilité de phase
laser(oscillateur)-horloge(500MHz). La phase
commence à bouger quant linac |
|
|
544
|
Mon Sep 12 18:03:04 2022 |
MJ, VC, HG | Under Process | Info | Linac Commissionning |
|
Mesures Linac Alignement | | - Affinage axe mag LIL
- Meses axes mag Quad à analyser
On fini demain, et on remplira |
|
|
543
|
Fri Sep 9 18:26:51 2022 |
Entered by Moutardier Alexandre from 134.158.195.145 on Fri Sep 9 18:26:38 2022 | | Info | Diag |
|
First injection in the ring | | Injection dans l'anneau.
Signaux sur les 5 premier BPM de
l'anneau without kicker. |
 |
|
542
|
Fri Sep 9 12:36:23 2022 |
Entered by Super Team from 134.158.195.141 on Fri Sep 9 12:36:09 2022 | Under Process | Shift summary | Diag | Linac Commissionning |
|
Shift Linac + TL + Injection | | Demarrage 12h30 :
- difficile, modulateur passe difficilement
en Trig |
|
|
541
|
Thu Sep 8 20:47:20 2022 |
Entered by Moutardier Alexandre from 134.158.195.142 on Thu Sep 8 20:47:07 2022 | Under Process | Info | Diag | Aimants |
|
Bilan des test avec feuille phosphorescente | | Instalation feuille phosphorescente au
niveau de la fourchette "by-pass/ring"
pour essayer de voir le faisceau |
|