| ID |
Date |
Author |
Status |
Type |
Category |
Important |
Subject |
Icon |
Text |
 |
|
1162
|
Thu Dec 4 08:59:07 2025 |
Entered by Super Team from 134.158.195.141 on Thu Dec 4 08:58:52 2025 | | Shift summary | LI | TL | Ring |
|
Preparation/check of the 70 MeV WP for X-ray run | | Goal: preparation and checking the machine
operation at 70 MeV and 40 MeV (ideally with
X-rays) |
  |
|
1046
|
Fri Mar 28 14:27:01 2025 |
Entered by Super Team from 134.158.195.141 on Fri Mar 28 14:26:38 2025 | | Linac | LI |
|
Prep faisceau pour lundi | | 12h47 Mise en chauffe modulateur
Zone de stockage en rouge
Mise en route frigo, chillers : |
|
|
256
|
Fri Jan 14 15:44:53 2022 |
Entered by Alexandre Moutardier from 134.158.195.142 on Fri Jan 14 15:44:40 2022 | | Info | Diag | Linac Commissionning |
|
Premier faisceau OTR ! | | Première lumière OTR
pris sur la station TL/DG/SST.01 !
Images are without and with background |
 |
|
326
|
Fri Feb 11 15:07:56 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Fri Feb 11 15:07:41 2022 | Fixed | Problem | Linac Commissionning |
|
Positions moteurs M4-1(2) | | Positions moteurs
LI/OP/OPT.01-Mir.04-MOP.01
-> =190mm ??? |
|
|
1185
|
Wed Jan 21 07:56:59 2026 |
KD MJ RC DN | Under Process | Shift summary | LI | TL | LE | Ring | Linac Commissionning | Ring Commissioning |
|
Position Horiz FPC ("spectres dromadaires") | | 7h55: mise en chauffe en remote (modulateur,
cyclage, laser, frigo/chillers)
==> plus de trig sur la machine |
|
|
140
|
Thu Oct 28 17:25:53 2021 |
Entered by sophie chance from 134.158.195.141 on Thu Oct 28 17:25:40 2021 | Fixed | Info | Vide |
|
Pompe PP1 | | Lorsqu'il y a une coupure de courant
la pompe PP1 remet une valeur d'interlock
par défaut qui n'avait pas été |
|
|
442
|
Thu Apr 14 11:05:07 2022 |
Entered by IC/V/SC from 134.158.195.141 on Thu Apr 14 11:04:51 2022 | Under Process | Linac | Linac Commissionning |
|
Polarités des quadrupoles | | Faisceau en route, visualisation sur TL/DG/SST.01
Bobine focalisation : 190 A, LI/PS/STR.01-H01
= -1A, LI/PS/STR01-V01 = 1A, Faisceau quasi |
|
|
Draft
|
Tue Oct 4 17:34:09 2022 |
Entered by Nicolas Delerue from 134.158.88.175 on Tue Oct 4 17:33:52 2022 | | Shift summary | |
|
Planning shift Thursday 6th October | | - Study beam position on SST and BPM vs
iris size / TL/BPM.01
- Start AcQAttrManager |
|
|
286
|
Mon Jan 31 10:03:50 2022 |
Entered by Super Team from 83.202.31.199 on Mon Jan 31 10:03:38 2022 | Fixed | Linac | Linac Commissionning |
|
Planning cette semaine | | -----------------------------------------------------------------------------------
Planning de la semaine
Lundi |
|
|
424
|
Mon Apr 4 10:50:19 2022 |
Entered by Super Team from 83.202.31.199 on Mon Apr 4 10:50:04 2022 | Fixed | Info | Linac Commissionning |
|
Planning cette semaine | | |
 |
|
499
|
Thu Jul 7 11:13:26 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Thu Jul 7 11:13:10 2022 | Fixed | Info | Linac Commissionning |
|
Phototube_Signal | | |
|
|
4
|
Tue May 28 15:07:37 2019 |
Entered by Aurélien Martens from 134.158.88.183 on Tue May 28 15:07:25 2019 | Fixed | Info | Tango |
|
Photocathode laser DS back operational |
| Following:
1) a crash on 4th of April
and a violent reboot of the ELLiOOs |
|
|
545
|
Tue Sep 13 11:49:50 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Tue Sep 13 11:49:29 2022 | Fixed | Info | Linac Commissionning |
|
Phase Stability | | Bonjour, voici la stabilité de phase
laser(oscillateur)-horloge(500MHz). La phase
commence à bouger quant linac |
|
|
243
|
Tue Jan 11 19:30:19 2022 |
Entered by Nicolas Delerue from 134.158.195.141 on Tue Jan 11 19:30:03 2022 | Fixed | Fix | SY |
|
Pb declenchement scope synchro | | La frequence des diags etait reglee a 0.1Hz
et le scope de la salle de controle se declenchait
sur les diags. C'est pour cela que le |
|
|
253
|
Fri Jan 14 12:35:13 2022 |
Entered by Super Team from 134.158.195.142 on Fri Jan 14 12:35:01 2022 | Fixed | Info | Linac Commissionning |
|
Pause déjeuner | | Ne pas toucher les réglages, merci |
|
|
134
|
Thu Oct 28 13:46:37 2021 |
Entered by sophie chance from 134.158.195.141 on Thu Oct 28 13:46:25 2021 | Under Process | Linac | Linac Commissionning |
|
Passage à énergie max | | Solenoide à 140A , attenuateur canon
3 dB, difficile de passer les 150A
Passage à Energie max |
|
|
972
|
Tue Dec 3 09:14:50 2024 |
SC, HG, VM | Under Process | Linac | LI | TL |
|
Passage à 61.5MeV et 70 MeV | | 9h14 Mise en chauffe
Pas de camera laser qui s'ouvre
sur PlateformeIHM |
 |
|
145
|
Fri Oct 29 13:57:49 2021 |
Entered by sophie chance from 134.158.195.142 on Fri Oct 29 13:57:22 2021 | Under Process | Linac | Linac Commissionning |
|
Passage section | | Le faisceau a passé la section
STR01-V01 = -1.10, STR01-H01 =
-1.90 |
|
|
887
|
Fri Jul 19 14:59:48 2024 |
Entered by Nicolas Delerue from 193.55.29.173 on Fri Jul 19 14:59:34 2024 | Fixed | Fix | Opt |
|
Passage a 25Hz IHM conditionnement | | Le bouton pour passer le conditionnement
à 25Hz a été ajouté
sur l'IHM conditionnement. |
|
|
391
|
Tue Mar 8 13:22:01 2022 |
Entered by SC/MO/CB from 134.158.195.142 on Tue Mar 8 13:21:48 2022 | Fixed | Linac | Linac Commissionning |
|
Paramètres faisceau du jour | | Attenuateur canon = 0dB
Energie mesurée =
50 MeV |
|