  Toutes les notes concernant les Commissionning de ThomX, Page 33 of 59  Not logged in ThomX    logo
Entry   Entered by Marie Jacquet from 134.158.89.45 on Thu Oct 13 17:41:00 2022; Alignement LINAC (canon-LIL-QUADs) 2022-10-13-elog.pdf
Entry   ND, VC, KD, VK; Operations du 13/10/2022 Screenshot_from_2022-10-13_14-44-35.pngscan_charge_phase.png2022-10-13_17_16_21_tl_dg_sst_03-ccd_01_log_scale_False_despeckle_False_min_scale_0_max_scale_150.pngcamera_delay_scan_full.pngcamera_delay_scan.png
   +  Reply   ND; RE: Shift du 12/10/2022 (prise de données) 
Entry   HG/CB; run du 11/10/2022 BPM_saturation_2022-10-11_15-07-37.png
Entry   Entered by Marie Jacquet from 134.158.89.45 on Tue Oct 11 11:09:03 2022; Valeurs des BPM LI et TL_1 surestimees ? 2022-10-11-BPM-YAG-STR.pdf
Entry   Entered by Viktor Soskov from 134.158.195.153 on Mon Oct 10 17:19:55 2022; Laser status 
Entry   Entered by Viktor Soskov from 134.158.195.153 on Mon Oct 10 15:10:21 2022; Laser status 
Entry   KD, VS, SC; shift du 10 octobre 2022 
Entry   IC, VM, VK, AL, JH; Optimization of the ring 6x
Entry   Entered by Marie Jacquet from 88.165.97.136 on Fri Oct 7 00:30:03 2022; shifts LINAC 4/10 et 6/10 
Entry   VK/ND/SC; Faisceau Anneau 10x
Entry   VK, VM, HG,IC, AL;  
Entry   Entered by Nicolas Delerue from 134.158.88.175 on Tue Oct 4 17:33:52 2022; Planning shift Thursday 6th October 
Entry   MJ/HG/SC; Alignement linac 
Entry   VK, AL, IC; Beam is stored 6x
Entry   VC/KD/SC; Faisceau linac 
Entry   Slava, Viktor M, Iryna; Check the QUADs in the ring 
Entry   AM, VI, VK, IC, VC, ND; Shift du 30/09/2022 16x
Entry   AM, IC, VK, VI, SC, ND; Shift du 29/09/2022 9x
Entry   Entered by Marie Jacquet from 134.158.89.45 on Wed Sep 28 19:13:52 2022; Shift du 12-13/09 en image  2022-09-28-elog.pdf