ID Date Author Statusdown Type Category Important Subject Icon
  1241   Wed May 13 08:35:16 2026 Entered by Super Team from 127.0.0.1 on Wed May 13 08:35:01 2026Under ProcessOtherLI manip Gplast 

demarrage machine 8h30

faisceau ok vers 10H

14h mesure 50 MeV

16h : passage à 8MeV 

  Draft   Wed Jun 3 08:54:55 2026 IC, VMUnder ProcessUrgentLI | RF Anneau Restart of the accelerator 

08h45 Start-up modulator, laser, magnets

09h38 Shutter Laser Linac is yellow. Tuning off the gun operation key does not change it to the red. Need help.

09h55 HV is on

09h56 HV is off. The fridge was started then chillers.

10h20 The laser shutter is OK.  HV is on

recipe_recipe_LI_TL_RI_all_20260422_18_34_34.txt loaded

Linac steerers were adjusted.

11h35 Energy = 50 MeV, Laser Phase 9 dg., Sect. Phase 223 dg., Sect. Att. 2.19 dB, I_Gun -48.3388 pC, I_Linac -54.8343 pC, I_TL -53.5573 pC RF_Ampl. 0 kV, RF_Phase -30.5 dg.

Beam is in the ring W/O RF

11h45 RF is on

11h54 Energy = 50 MeV, Laser Phase 9 dg., Sect. Phase 223 dg., Sect. Att. 2.12 dB, I_Gun -49.1448 pC, I_Linac -55.6953 pC, I_TL -54.5153 pC RF_Ampl. 49.3668 kV, RF_Phase 35.5 dg.
It looks like RF cavity tuning does not work. Help is needed.

12h07  Mesure d'energie en sortie canon sur LISST1 en fonction du courant du steerer LI/PS/STR.01-H.01

'Energy=4.83MeV'

Several scans of the laser attenuator 200 to 430 at the Gun attenuator 0, 1, 2, 3 dB but at the same phase.

13h22 Standby

13h32 HV is on

15h17 Thomx was stopped

 

Attachment 1: GunCharge_vs_LaserAtt.png
GunCharge_vs_LaserAtt.png
Attachment 2: GunDarkCurrent_vs_Att.png
GunDarkCurrent_vs_Att.png
  Draft   Wed Jun 17 08:36:20 2026 IC, VMUnder ProcessProblemVide Restart of the accelerator 

08h35 Start-up modulator (it was already on standby), laser, magnets, cycling.

As yesterday there is a problem with the MPS to start the machine. We are trying to investigate whether it is related to the vacuum or something else.

Problem with the solenoid COL.01 (Internal Interlock Hard).

Help is needed.

At this moment, apparently we are blocked by the closed vacuum valve of the FPC. To be checked with Nourredine (emails sent).

The vaccum level in the FPC is not yet good to open the valve. Eric will check it.

10h10 Switched to the Linac+TL+EL configuration. HV is on (the modulator was in the local mode). Interlocks even at HV 1200 V, the sect att. 3 dB. Linac 04 vac is high.  

10h33 There are breakdowns at 26 dB the section att. and 25 dB of the RF gun att. These are not in vacuum breakdowns. Probably it is the klystron problem.

10h50 The modulator is in the standby mode.

Maher is coming to check the klystron and Jean-Noel is working on the solenoid power supplies.

11h40 Maher fixed problem with the klystron by increasing the filament power. At 84 kV, I = 48.7 A (microperveance 2.0). At 293 kV, I = 294 A (microperveance 1.85, should be 2.0).

12h03 The machine configuration without FP closes the photocathode laser shuter, so we can operate only in the Linac+TL+EL configuration.

12h36 Energy = 50 MeV, Laser Phase 25 dg., Sect. Phase 253 dg., Sect. Att. 2.26 dB, I_Gun -95.0704 pC, I_Linac -92.7397 pC, I_TL -3.7568 pC RF_Ampl. 0 kV, RF_Phase 35.5 dg.

Laser Att. 360, Linac steerers H: [0.31 -2.62], V: [-1.87 2.88]

12h43 Energy = 50 MeV, Laser Phase 26 dg., Sect. Phase 250 dg., Sect. Att. 2.35 dB, I_Gun -101.3924 pC, I_Linac -99.5194 pC, I_TL -101.3812 pC RF_Ampl. 0 kV, RF_Phase 35.5 dg. 

13h17 Laser Att. 410 (max) Energy = 50 MeV, Laser Phase 26 dg., Sect. Phase 250 dg., Sect. Att. 2.35 dB, I_Gun -138.8712 pC, I_Linac -135.3968 pC, I_TL -137.4172 pC RF_Ampl. 0 kV, RF_Phase 35.5 dg.

At the moment maximum charge is 135 pC with irise Ø of 1.3 mm  (possibly because the laser photocathode shutter is in the wrong position)

13h25 The modulator is in standby mode. Maher can remove the MPS short.

The problem with MPS is the OC/AVAL02 FP valve. It is in two states at the same time: Closed and Open.

It was the OC/AVAL01 FP valve

recipe_recipe_LI_TL_RI_all_20260422_18_34_34.txt loaded

14h54 Beam is in the ring w/o RF. Thank you all !!!!.

15h15 Laser Att. 360,  Energy = 50 MeV, Laser Phase 26 dg., Sect. Phase 250 dg., Sect. Att. 2.42 dB, I_Gun -179.1795 pC, I_Linac -205.8011 pC, I_TL -186.6367 pC RF_Ampl. 99.1184 kV, RF_Phase -50 dg.

Laser Att. set to 320 for 100 pC

15h25 Energy = 50 MeV, Laser Phase 26 dg., Sect. Phase 250 dg., Sect. Att. 2.33 dB, I_Gun -96.7941 pC, I_Linac -124.7882 pC, I_TL -102.9734 pC RF_Ampl. 99.1184 kV, RF_Phase -50 dg.
 

15h28 recipe_recipe_LI_TL_RI_all_20260121_10_35_05.txt loaded. There is storage, but it is necessary to optimize it

15h33 ring_saving

15h35 recipe_recipe_LI_TL_RI_all_20260422_18_34_34.txt loaded

15h36 ring_saving

17h41 ThomX was stopped

Attachment 1: Screenshot_from_2026-06-17_15-54-18.png
Screenshot_from_2026-06-17_15-54-18.png
Attachment 2: Screenshot_from_2026-06-17_15-50-21.png
Screenshot_from_2026-06-17_15-50-21.png
  35   Fri Jun 11 18:47:23 2021 HaygReference SolutionLinacRF D1 DS pour les températures des chillers icon1.gif 

Listes des Ds pour les températures des chillers

  • GUN : ER/HF/RAC.17-API.AI1/AI2
  • Section : ER/HF/RAC.17-API.AI1/AI1

Emplacements :

  • Sortie Chiller : AI1 en Volt
  • Sortie Clarinette : AI2 en °C
  • PT100 Structure : AI3 en °C
  51   Thu Jul 15 12:39:56 2021 Entered by Kevin Dupraz from 134.158.195.153 on Thu Jul 15 12:39:32 2021Reference SolutionInfoOpt | Linac Commissionning Alignement PhotoCathode 

L'alignement de la PhotoCatode est fini. Il est a noter :

- La position de la camera a ete ajuste pour mieux coller a la distance entre PhotoCathode et miroir de prelevement (pour la cathode virtuelle). Cette distance est d'environ 215.5 cm.

- le tube a vide d'entre du laser dans le linac a ete retire pour s assurer de l alignement du laser sur le miroir sous vide. Le faisceau est centre en transverse et legerement au dessus de l horizontal en vertical (<3/4 du miroir environ)

- L'image de reference de l'alignement Photocathode est en piece jointe. Le faisceau est centre sur la camera.

- les alignement ont ete revu au niveau de la table de la casemate pour reduire le vignetage

- L'energie UV en sortie du laser etait de 140uJ environ.

 

Point a faire et a surveiller :

- Il faut remettre le tube d'injection et passer sous vide

- Il faut mesurer la puissance laser sur la table optique dans la casemate

- le shutter de securite semble disfonction en mode local. Il y a une repercution sur le PSS (defaut a aquitter)

- L'attenuateur ne semble pas tourner.

 

Attachment 1: Image__2021-07-15__12-34-45_PCVirtuelle.bmp
  52   Thu Jul 15 15:49:36 2021 Entered by Kevin Dupraz from 134.158.195.153 on Thu Jul 15 12:39:32 2021Reference SolutionInfoOpt | Linac Commissionning RE: Alignement PhotoCathode 

Le tube de liaison a ete remis, le faisceau etait legerement decale. Il a ete realigner sur la PhotoCathode (1mm a gauche de la sortie de la PhotoCathode trouee).

La nouvelle image et en P.J.

La référence sur la position moteurs des miroirs est :

li/op/las.01-mir.05 :

* mot.01 : - 0.180 mm

* mot.02 : - 1.035 mm

li/op/opt.01-mir.04 :

* mot.01 : 0 mm

* mot.02 : 27.01 mm

Je déconseille de se fier à cela. Il y a beaucoup d’hystérésis. Ce qui fait fois est la position sur la caméra.

Pour info : Compressor Position : 119988

Entered by Kevin Dupraz from 134.158.195.153 on Thu Jul 15 12:39:32 2021 wrote:

L'alignement de la PhotoCatode est fini. Il est a noter :

- La position de la camera a ete ajuste pour mieux coller a la distance entre PhotoCathode et miroir de prelevement (pour la cathode virtuelle). Cette distance est d'environ 215.5 cm.

- le tube a vide d'entre du laser dans le linac a ete retire pour s assurer de l alignement du laser sur le miroir sous vide. Le faisceau est centre en transverse et legerement au dessus de l horizontal en vertical (<3/4 du miroir environ)

- L'image de reference de l'alignement Photocathode est en piece jointe. Le faisceau est centre sur la camera.

- les alignement ont ete revu au niveau de la table de la casemate pour reduire le vignetage

- L'energie UV en sortie du laser etait de 140uJ environ.

 

Point a faire et a surveiller :

- Il faut remettre le tube d'injection et passer sous vide

- Il faut mesurer la puissance laser sur la table optique dans la casemate

- le shutter de securite semble disfonction en mode local. Il y a une repercution sur le PSS (defaut a aquitter)

- L'attenuateur ne semble pas tourner.

 

 

Attachment 1: Image__2021-07-15__12-34-45_PCVirtuelle.bmp
  89   Tue Oct 5 10:05:21 2021 Entered by Hayg Guler from 134.158.195.141 on Tue Oct 5 10:05:07 2021Reference SolutionLinacLaser Comment éteindre le laser icon3.gif 

Pour couper le Laser :

  • il faut arrêter seulement l'Ampli, et laisser l'oscillateur (pas besoin de l'arrêter).
  • Redémarrer l'oscillateur peut le mettre dans un mode instable.

 

  176   Tue Nov 23 12:11:16 2021 Entered by Super Team from 134.158.195.141 on Tue Nov 23 12:11:01 2021Reference SolutionInfoLaser | Linac Commissionning energie laser 

La puissance laser aujourd'hui (23/11/2021) est de :

  - Sortie laser : 200 uJ
  - Sortie ligne de transport : 60 uJ
  - Injecté dans le canon (iris ouverte à 100%) : 47 uJ

La transmission de la ligne de transport est en baisse. Les Hublots sont en cause. Il faut augmenter la taille sur le hublot ou changer le coating de ce dernier.

Hublot d'entrée retiré :

- Puissance laser sortie ligne de transport : 105 uJ

 - Puissance iris ouverte 100% : 73 uJ

Kevin

  235   Wed Jan 5 17:35:11 2022 Entered by Super Team from 134.158.195.141 on Wed Jan 5 17:34:46 2022Reference SolutionInfoLaser | Linac Commissionning Iris Motorisé 

[KD et HG]

-  Mise en place de l'iris motorisé à peu près à l'endroit ou se trouvait l'autre iris (+/- 1 cm).

- Le Ds doit être installé par le CC

 

  417   Thu Mar 24 17:12:01 2022 Entered by ND/VC/HG/SC from 134.158.195.142 on Thu Mar 24 17:11:44 2022Reference SolutionLinacLinac Commissionning Paramètres Faisceau 

Alignement laser

On retrouve la phase pour la charge max phi = 313 degres (consigne chiller canon = 31.25 degres)

On enlève 40 degres à la phase de charge max pour arriver à la phase d'énergie maximum phi = 273 degres

On focalise le faisceau avec la bobine de sortie canon I = 170 A

On peut l'observer sur la camera LI/DG/SST.01

On passe ensuite la section phi section = 100 degres (consigne chiller section 28.95 degres)

On met du courant dans le steerer avant section LI/PS/STR.02-V.01 I = 0.83A et LI/PS/STR.02-H.01 I = -0.90A

On observe sur TL/DG/SST.01

On peut observer les trends des ICTs avec taurus plot er/ca/rac.05-elr.01_wac.02/ch0 pour ICT1

  574   Mon Oct 3 20:31:09 2022 VK, AL, ICReference SolutionShift summaryRing Commissioning Beam is stored 

Shift started at 18h

With the current injector settings, it was difficult to inject.  We loaded the settings from last Friday 30/09 (19-22-04).

 

Principal steps:

- Correction of the one quadrupole polarity this morning

-injection tuning, observation of Turn-by-Turn-X, Turn-by-Turn-Y and Sum

-quads focusing, defocusing +-.0.5%

-iterative manual adjustments of corrctors, DPI, Septum, Kicker

-orbit correction with open line model response matrix 

- several datasets taken for further postprocessing

 

Beam is stored !!!!! ~400 turns (limited by the Libera response)

 

Stored beam, visible  more than 300 turns,  signal decay as estimated  due to Libera cutoff filters. To store more, RF cavity should be used.

Stable closed orbit!

Important milestone is achieved.

No losses at scintillator/fiber except for the injection, see oscilloscope screenshot.

Current machine settings are stored in recipe_recipe_LI_TL_RI_20221003_20_24_01.txt

Orbit is stable for more than one hour. End of the shift.

 

 

 

Attachment 1: Screenshot_from_2022-10-03_20-34-31.png
Screenshot_from_2022-10-03_20-34-31.png
Attachment 2: Screenshot_from_2022-10-03_20-27-05.png
Screenshot_from_2022-10-03_20-27-05.png
Attachment 3: Screenshot_from_2022-10-03_20-26-19.png
Screenshot_from_2022-10-03_20-26-19.png
Attachment 4: Storage_TbTsummary2_03102022.png
Storage_TbTsummary2_03102022.png
Attachment 5: Storage_TbTsummary1_03102022.png
Storage_TbTsummary1_03102022.png
Attachment 6: closed_orbit_03102022.png
closed_orbit_03102022.png
  737   Thu Apr 20 10:36:19 2023 Entered by Super Team from 134.158.195.142 on Thu Apr 20 10:36:01 2023Reference SolutionShift summaryLI | TL | Aimants | Linac Commissionning référence axe mag Canon 

Voici la référence tete de machine pour l'axe mag canon :

Laser Iris position  [H;V] : [4.90/2.42mm]

Solénoides position : Z : 3.3mm, -4.9mrad

                                 X : 0.8mm, 10.201mrad

  762   Wed Jun 7 16:02:33 2023 LS, MB, VC, NDReference SolutionShift summaryRing Programme prise de donnees 8/06 

9:23 Mise en chauffe

Nombreux pb vide dans health check

Acces casemate pour verification polarite RI-C2/DG/BPM.02 pas de probleme trouve.

Observation des soufflets pres de RI-C2/AE/DP.04 ils semblent legerement deformes mais pres de RI-C1/AE/DP.01 aussi.

11:30 Tentative de demarrage mais probleme temperature eau...

12:00 Intervention Maher. Demarrage possible.

Pb declenchement wavecatcher... Resolu (le serveur etait plante)

14:00 BPM polarity studies

15:30 Measure frequency

16:30 To to steer the beam around the chamber

18:20 Stop

 

===

Programme de la prise de données du 8/06:

0) During warm up:

0a)check physically BPMs where there seem to be a polarity issue (needs 2 persons, a battery and a multimeter).

0b) CHeck vacuum chamber around RI-C2/AE/DP.04

1) Transport to TL/FC.01 (TL/DP.01 off). Record FC  signal

2) Transport to TL/SST.02 and TL/BPM.02. Record BPM adc signal while closing dispersion (for Mouad's studies).

3) Transport to EL/FC.01. Record FC  signal and compare with TL/FC.01. If needed swap filters and compare again.

4) Activate position feedback on TL/BPM.02

5) Inject in ring, no RF power. Record with high res oscilloscope travel time for different magnets settings. If needed use a mixer.

6) Study the effect of correctors around RI-C2/AE/DP.04

7) Use extraction kicker scan to measure beam travel time after several turns

8) Finish BPM polarities study

9) Repeat (5) and (7) with different RF powers at 2 different frequencies (500.0202MHz and 500.4MHz). Look at oscillations on TbtX and TbtY vs frequency.

 

Attachment 1: health_check_2023_06_08_09_30.png
health_check_2023_06_08_09_30.png
Attachment 2: health_check_RF_2023_06_08_09_30.png
health_check_RF_2023_06_08_09_30.png
Attachment 3: health_check_Vide_2023_06_08_09_30.png
health_check_Vide_2023_06_08_09_30.png
Attachment 4: health_check_Alimentation_2023_06_08_09_31.png
health_check_Alimentation_2023_06_08_09_31.png
  796   Wed Sep 27 12:38:08 2023 KDReference SolutionShift summarySY | Linac Commissionning run du 27 septembre 2023 

12h38 : Mise en chauffe de la machine (modulateur, chiller, laser)

==> mise en place de la version du 27/09 dans le CPLD pour la synchro. Trig régulier mais jitter entre les deux 500MHz de 35 ps (RMS) et 160 ps (P-P).

17h30 : arret machine

Programme : 

* Redemarrage de la machine

      -> charge eviron de 200 pC à 310mm de attenuateur et 1.3mm ouverture iris

             * Energie max : 155° (phase canon), 100pC à 530mm atténuateur laser, position [H;V] = [5.24 mm, 2.91mm]   

* verification du trig Klystron

  -> pas de probleme de klystron visible. Le faisceau est pas mal "bruyant", il saute sur les écrans

* élaboration d'une recette pour injection dans l'anneau

   -> faisceau transporte jusqu'a l'écran TL/SST.03 ==> le faisceau est très décalé sur la droite (meme avec la recette precedente le faisceau est décalé "all_20230825_16_57_06")

   -> recette sauvegardé : "all_20230927_17_10_22"

à finir au moment de l'injection de demain

  800   Thu Oct 5 08:39:05 2023 Entered by Super Team from 134.158.195.141 on Thu Oct 5 08:38:51 2023Reference SolutionShift summaryLaser | Opt | Linac Commissionning | Ring Commissioning run du 5 octobre 2023 

8h30 : mise en chauffe de la machine

 

*** Comment aires ***

- test programme CPLD avec reste sur 2e fronts 41 MHz (oscilloscope nécessaire pour vérifier les signaux)

*** Programme ***

- Stocker de la puissance dans la cavité

- stocker le faisceau d'électron dans l'anneau (à 500.25 MHz est le mieux)

- chercher les rayons X en mode désynchronisé

- Chercher la synchro des rayons X avec l'anneau

  801   Fri Oct 6 18:45:56 2023 KDReference SolutionShift summaryLaser | Opt | Linac Commissionning | Ring Commissioning run du 6 octobre 2023 

17h: Pris en main de la machine (anneau à 500.34MHz). Qualité du stockage très aléatoire (bruit de synchro). 

* Cavité locké avec une CEP très dégradée à 9kW en moyenne.

- Position table optique initial (X de juillet) : TZ = -1.652mm

- Position à 500.34MHz cavité RF : TZ = -2.06 mm (à affiner)

* essaie de mettre l'anneau à 500.25MHz ==> Auncune recette ne marche pour l'injection (meme en variant la valeur kicker, septum, phase, puissance). 

==> nécessité de mettre en place des recettes viable et des procédures pour stocker dans l'anneau.

 

18h45 : arret machine

  Draft   Tue Oct 10 09:02:36 2023 KDReference SolutionShift summaryLinac Commissionning | Ring Commissioning shift du 10 octobre 2023 

9h: mise en chauffe de la machine

- La clé PA est resté enclenchée, les lumières allumées. Qui a pris la machine hier ?

11h15 Démarrage de l'archivage. 

 

*** Programme ***

- Stockage anneau à 500.25MHz

- Stockage puissance CFP (> 10kW) 

- chercher les rayons-X en désynchronisé à 500.25MHz

- synchroniser la machine (Anneau + CFP)

- Estimation du flux obtenu en synchronisé

  805   Wed Oct 11 09:07:49 2023 KDReference SolutionShift summaryLaser | Opt | Linac Commissionning | Ring Commissioning shift du 11 octobre 2023 

9h: mise en chauffe de la machine

* injection dans l'anneau avec la recette 500.25MHz

* lock de la cavité et rayons-X retrouvé (en désynchronisé)

* essaie de synchroniser la cavité sur le 500.25MHz et scan en phase

==> beaucoup de problème technique (cable de controle de la phase 33MHz débranché, stabilité de la machine)

* X synchronisés non stable car le schéma de synchronisation ne verrouille pas le numéro du bucket RF de l'anneau (asynchrone sur le 33MHz, synchro utilisé : 8x8 ==> 41MHz)

     -  de pic plus régulier apparaissent puis disparaissent (surement en fonction de la synchronisation "glissante" entre le 41MHz et le 33MHz)

==> imposible de trouver une phase correcte avec un flux important régulier

* changement de la synchro (8x8 ==> 41x33 ==> 41MHz)

==> déphaseur 33MHz sur le laser CFP (le géné fait office de déphaseur quand la machine est sans la CFP)

* impossible en l'état de faire un scan sur le bucket du 500MHz :

     - changement de 500MHz implique un changement de phase du 33MHz et donc un changement sur la phase du trigger de la machine ==> donc changement de phase au niveau de la cavité RF

     - il faut compenser le changement de phase 500MHz (CFP) par un changement de phase 33MHZ (CFP)

    - Puis changer de numeros de bucket RF et recommencer le scan sur le 500MHz

17h30 : arrêt machine

 

*** Programme ***

- Locker la cavité FP sur la fréquence anneau

- Trouver la phase du bucket RF 500MHz

- estimer le flux de rayons-X

- essayer de synchroniser totalement la machine

- trouver le bon numéro du bucket RF

- estimation du flux de rayons-X

  806   Wed Oct 18 10:08:24 2023 KD, MJ, HG, DN, IC, & al.Reference SolutionShift summaryLaser | Opt | SY | Linac Commissionning | Ring Commissioning shift du 18 octobre 2023 

10h : mise en chauffe de la machine (chillers, modulateur, laser, alims).

*** Programme ***

- Stockage des e- et puissance laser

* Stockage dans l'anneau immédiat avec la recette (ajustement linac : phase et attenuateur, pres)

* Problème avec la cavité RF, phase étrange (faisceau tué après quelque us) ==> il faut aller loin dans le scan de phase

* injection réajusté par Iryna

* Cavité locké à 8kW 

- synchronisation CFP sur horloge machine (une fois les rayons-X trouvés/observés en mode désynchro)

* rayons-X trouvé (4pA dans le détecteur fluo)

*  essaye de synchronisation (rebranchement du cable 33MHz CFP) ==>  pas assez de signal ==> ajout d'un ampli dans la synchroBOX

- scan du buket RF (scan déphaseur 500MHz CFP avec compensation déphaseur 33MHz CFP)

* Impossoble de faire des scans : pas assez de stabilité (juste pour retrouver la phase RF avec la cavité

- scan des numéros de bucket

* changement du programme CPLD (une basule) pour ne pas etre synchrone avec le 33MHz (33x33 ==> 41MHz)

==> on ne trouve rien également le changement du bucket RF n'est pas assez régulier. Mais on dégrossis la phase 500MHz (environ 7V sur le dephaseur 500MHZ CFP)

* Remise du programme CPLD précédent : (33x33 ==> 33x41 ==> 41MHz avec ligne à retard externe)

* scan du bucket RF avec le géné 33MHz (24° à 33MHz = 360° à 500MHz)

==> ca marche et c'est répétable il faut pour cela :

** mesurer la phase entre le 33MHz CFP et le trig (pour avoir le bucket RF)

1) Locker la cavité CFP sur le 500MHz

2) "mesurer" le bucket accroché (aujourd'hui, trig pris dans l'igloo et le 33MHz CFP en sorti de déphaseur 0V de consigne)

3) déphaser le géné pour retrouver le bucket RF correct (équivalent à 26.5ns de delai entre le trig et le 33MHz CFP), la phase de référence sur le géné était de 53.5°

recommencer à chaque délock de la cavité.  

==> on gagne un facteur 100 au niveau du flux. A affiner, il manque un facteur 10 qui peut venir de : jitter synchro ou CFP ?

La puissance laser et la charge stockée sont pris en compte au niveau du signal de référence en non synchronisé (3-4 pA), on doit avec la synchro avoir un facteur 1000 environ.

 

17h35 : arret machine 

Attachment 1: Screenshot_2023-10-18_17-15-49.png
Screenshot_2023-10-18_17-15-49.png
Attachment 2: scrprint.png
scrprint.png
  815   Thu Nov 9 09:02:39 2023 KDReference SolutionShift summaryLI | TL | LE | Ring | Diag | CC | Laser | Opt | RF Anneau | SY | Linac Commissionning | Ring Commissioning shift du 09 novembre 2023 

8h30 : démarrage machine (laser, klystron, chiller, frigo, aimant)

* Beaucoup de problème de rédémarrage. Les delays au niveau des wavecatcher ne sont toujours pas bons (pas de signal de charge visible).

* Problème sur le géné 33MHz à la mauvaise fréquence (en Hz au lieu d'être au MHz) empécher le système de synchronisation de fonctionner (pas de Trig).

* Problème sur la puissance en sortie du synthé 500MHz RI, rédémarrage effectué (ce qui à engendré un problème sur le Géné 33MHz qui n'était plus synchrone du 10MHz).

==> mise en place d'une recette d'injection dans l'anneau, basée sur la recette précédente (recipe_recipe_LI_TL_RI_all_20230928_15_43_43.txt) et sur le nouveau point photoCathode trouvé les semaines précédente. Injection à  optimisée car le stockage est "plat" sur 100ms mais il y a peu de charge stocké (qq 10^6 sur les BPM)
recette sauvée sous : recipe_recipe_LI_TL_RI_good_20231109_15_00_00.txt

* Il semblerait que la consigne de phase au niveau du LLRF de la cavité RF ne fonctionne pas.

 

15h30 : arrêt machine

 

*** Programme ***

- Allumer les équipements au fur et à mesure pour voir l'influence sur le lock de la cavité FP

Tout les équipements ont été allumé un par un jusqu'au stockage dans l'anneau, peu d'effets sont visible sur le stockage de la cavité. Quelques perturbations difficiles à identifiés se sont produite de façon intermitentes.

- Synchroniser la cavité à l'anneau

Un problème sur le signal de synchronisation est apparu et a été résolu (une alimentation d'un ampli sur le signal d'erreur de la cavité). Par manque de temps la cavité n'a pas été asservis sur l'horloge machine.

Le DS pour le moteur de la cavité n'est toujours pas ajouté à JIVE malgrè un ticket ouvert depuis 2 semaine

- Optimiser la synchronisation e-/laser