Draft
|
Thu Mar 7 08:58:28 2024 |
VK, VM, IC | Under Process | Shift summary | Ring Commissioning |
|
Recomissioning of the SR, search for the X-rays | | 8h50 Warming up the machine
Problem with the vaccum around
the RF cavity (see screenshot attached). |
|
|
1062
|
Wed Apr 30 08:51:08 2025 |
VC, DN, MJ, IC, VM | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
Recherche position image camera MRSV | | Start chauffage 9H
There were some problems: the phase
section motor was in the wrong position, |
   |
|
168
|
Wed Nov 17 14:00:28 2021 |
Entered by Super Team from 134.158.195.142 on Wed Nov 17 14:00:15 2021 | Fixed | Fix | Diag | Linac Commissionning |
|
Recherche du signal ICT après la section | | Alexandre Moutardier :
Signal ICT (ER/CA/RAC.05-ELR.01-WAC.02
channel CH3) pas visible après |
 |
|
330
|
Mon Feb 14 10:12:10 2022 |
Entered by Moutardier Alexandre from 134.158.195.142 on Mon Feb 14 10:11:53 2022 | Under Process | Fix | SY |
|
Recette synchro | | Nouvelle recette synchro par défault
enregistré : 20220201_reference.xml
A tester en faisceau dans la journée. |
|
|
324
|
Fri Feb 11 14:15:57 2022 |
Entered by SC/HM/VC from 134.158.195.141 on Fri Feb 11 14:15:43 2022 | Fixed | Linac | Linac Commissionning |
|
Recette | | Recette sauvée : 20220211_1417.xml |
|
|
115
|
Tue Oct 12 15:36:08 2021 |
Entered by sophie chance from 134.158.195.142 on Tue Oct 12 15:35:55 2021 | Under Process | Linac | Linac Commissionning |
|
Radioprotection | | Mesures radioprotection en cours |
|
|
717
|
Fri Mar 17 08:55:42 2023 |
IC, VM, VK, ND | | Shift summary | Ring Commissioning |
|
RIng commissioning | | 8:50 Mise en chauffe
10h Starting the beam
Tuning of the TL |
10x |
|
754
|
Fri May 19 18:05:29 2023 |
VK, IC | | Shift summary | Ring Commissioning |
|
RF frequency of the Ring | | In the morning, after the start-up pf the
machine, scan phase-charge and small tuning
it was possible to store the beam with the |
   |
|
755
|
Fri May 19 20:22:42 2023 |
MJ, KD | Under Process | Shift summary | RF Anneau | Ring Commissioning |
|
RF et anneau | | Apres 18h30 : prise ne main de la machine
pour aller dans la LE ==> le kicker d'extraction
est interlocké (abdandon) |
 |
|
896
|
Fri Aug 2 11:00:49 2024 |
VM, HG, RC, SC | Under Process | Shift summary | RF D1 |
|
RF conditionning : 2 aout | | Start from 10 dB
decrease up to 1 dB : Vacuum is
OK decrease up to 10â»8 mBar |
|
|
132
|
Thu Oct 28 12:25:12 2021 |
Entered by sophie chance from 134.158.195.141 on Thu Oct 28 12:24:58 2021 | Under Process | Linac | Linac Commissionning |
|
RF + 5Hz + Solenoides | | Augmentation progressive du solenoide à
5Hz en cours |
|
|
222
|
Thu Dec 16 14:57:31 2021 |
Entered by Moutardier Alexandre from 91.168.92.148 on Thu Dec 16 10:39:49 2021 | | Info | CC |
|
RE: test en ssh | | Modifications faites, testées et
fonctionnelles.
|
|
|
689
|
Mon Feb 20 10:19:56 2023 |
ND | Under Process | Shift summary | LI | TL | LE | Vide | Linac Commissionning |
|
RE: shift du 20 février 2023 | | Healthcheck signal effectivement un probleme
sur toute les vannes... Et les atkpanels
signalent un problème de communication... |
 |
|
Draft
|
Mon Feb 20 10:16:18 2023 |
ND | Under Process | Shift summary | LI | TL | LE | Vide | Linac Commissionning |
|
RE: shift du 20 février 2023 | | Healthcheck signal effectivement un probleme
sur toute les vannes... Et les atkpanels
signalent un problème de communi |
|
|
673
|
Mon Feb 13 15:07:11 2023 |
Entered by Marie Jacquet from 134.158.195.141 on Mon Feb 13 13:34:44 2023 | Not Fixed | Problem | Linac Commissionning |
|
RE: problemes avec SST et YAGLI | | 1) Je viens de tenter de reproduire le
problème. Il est normal que cela mette
du temps à charger, surtout au premier |
|
|
621
|
Mon Oct 31 23:11:47 2022 |
ND | Fixed | Shift summary | Linac Commissionning |
|
RE: phase en delire | | Après un premier scan sur 0-360
degres le script lance un second scan sur
la zone la plus probable de maximum de charge |
|
|
341
|
Tue Feb 15 18:51:27 2022 |
Entered by Super Team from 134.158.195.141 on Tue Feb 15 17:37:50 2022 | Under Process | Linac | Linac Commissionning |
|
RE: nouvelle position miroirs | | Fin du run : 18h50.
Machine OFF
|
|
|
292
|
Tue Feb 1 11:29:30 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Tue Feb 1 10:43:30 2022 | Fixed | Info | Linac Commissionning |
|
RE: logiciel ihm | | Salut Viktor,
le Ds du Laser était arreté.
C'est ok maintenant. |
|
|
620
|
Mon Oct 31 23:09:07 2022 |
ND | Fixed | Shift summary | Diag | Linac Commissionning |
|
RE: ecrans yag 1 et 2 desinchro | | Je viens de regarder LI/SST.01 et TL/SST.01
étaient en attenuation maximale. Si
le problème se reproduit, il faut |
|
|
526
|
Mon Aug 8 17:05:30 2022 |
Entered by Moutardier Alexandre | Under Process | Info | Diag | Linac Commissionning |
|
RE: camera TL/SST2 + fente | | Voici une mise a jours concernant les fentes
:
- L'IHM fente |
|