873
|
Mon Jun 3 08:38:52 2024 |
MJ EK, KD, IC | Under Process | Linac | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
conditionnement section 03 juin | | 8H15 : Mise en chauffe modulateur
start frigo et chiller section
3 microsec 5 Hz attenu 6 dB (PIS |
13x |
|
875
|
Wed Jun 5 09:49:26 2024 |
MJ MK HG WK | Under Process | Linac | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
conditionnement section | | - On augmente l'attenuation pour démarrer
(7 dB)
- 2 µs @ 10 Hz |
    |
|
899
|
Thu Aug 8 10:12:35 2024 |
Entered by Super Team from 134.158.195.142 on Thu Aug 8 10:12:02 2024 | | Linac | LI | RF D1 |
|
conditionnement section | | Remplissage SF6 de 2.3 bar à 2.5
bar par Christopher
10h08 : augmentation progressive |
|
|
900
|
Fri Aug 9 10:01:23 2024 |
Entered by Super Team from 134.158.195.142 on Fri Aug 9 10:01:08 2024 | | Linac | LI | RF D1 |
|
conditionnement section | | Vide de démarrage apres l'allumage
des chillers : in section 6.4e-10 et out
section 8.3e-10 |
|
|
895
|
Thu Aug 1 08:43:29 2024 |
Iryna, Sophie, Viktor, Slava | | Shift summary | Linac Commissionning |
|
conditionnement de la section RF@ 3µs & 25 Hz | | 8h40 Warm-up the modulator
***
reprise de conditionnement @ 3µs |
14x |
|
830
|
Wed Jan 17 08:55:07 2024 |
VC-KD | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
commitionning | | 8H50
Demarrage chauffage, chiller, et
cyclage aimants |
10x |
|
834
|
Thu Jan 25 08:49:29 2024 |
VC DN ND, IC, VM, KD, AS RC , VK... | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
commitionning | | 8h45 demarrage chauffage Modulateur et
frigo
Pb sur le serveur li/opt.02-las.01-asp.01 |
27x |
|
836
|
Wed Jan 31 14:12:25 2024 |
RC VC MJ | Under Process | Other | Ring Commissioning |
|
commitionning | | Chauffage mod 11h
demarrage machine 14H
on suit le star faisceau step par |
 |
|
837
|
Thu Feb 1 08:10:14 2024 |
VK VC HG SC ME | Under Process | Shift summary | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
commitionning | | 8h10 rémarrage machine chauffage
klystron frigo et chiller
pB DS calc/er_sy/rac.17-elr.01-rdp.0X.Y |
|
|
842
|
Tue Feb 6 08:52:28 2024 |
VC MJ KD | Under Process | Shift summary | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
commissionning | | 8h45 demarrage machine
modulateur frigo ampli laser chiller
et cyclage des aimants |
7x |
|
843
|
Tue Feb 6 20:21:38 2024 |
Entered by Marie Jacquet from 134.158.89.45 on Tue Feb 6 20:21:21 2024 | Fixed | Shift summary | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
commissioning | | 14h - Mesures SPR radiations accelerateur
Beam shutter securite ne
remonte plus --> Mesure SPR X-hutch |
|
|
419
|
Fri Mar 25 08:22:18 2022 |
VC SC HG ND | Under Process | Linac | Diag | Linac Commissionning |
|
commisionning Charge et OTR | | demarrage Modulateur 8h20
9h15 temp chiller ok
energie laser 32uJ atténuateur |
12x |
|
878
|
Mon Jun 10 13:36:25 2024 |
KD, CJ, WE, GO, VC, ND | Under Process | Shift summary | Linac Commissionning |
|
claquage et test micros | | 9h: accès sous-sol
12h: démarrage modulateur
pour test micro (atténuateur à |
11x |
|
879
|
Tue Jun 11 08:44:30 2024 |
M EK, ND | Under Process | Linac | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
claquage et test micros | | 8:30 impossible de mettre en chauffe modulateur
Pompe ThomX HS
Dalkia a été contacté |
6x |
|
378
|
Tue Mar 1 11:53:20 2022 |
CB/JNC | | Problem | CC | Linac Commissionning |
|
charge phase | | Image laser sauvée à 11h50,
dimension rms 80 pixel en vertical et 94
en horizontal, position du laser : 934.34 |
|
|
1065
|
Tue May 6 11:38:24 2025 |
VS, AG, KD | New Solution | Info | LI | Laser | Opt | Linac Commissionning |
|
changement PhotoCathode |
| lundi 5 mai : remise à
l'air et démontage de l'ancienne
cathode (Cu) |
6x |
|
524
|
Wed Aug 3 11:30:54 2022 |
AM/SC/CB/JNC | | Fix | Diag | Linac Commissionning |
|
camera TL/SST2 + fente | | Intervention camera
Position YAG -64 mm, se mettre
en internal trigger manuellement sur jive |
|
|
610
|
Wed Oct 26 14:56:33 2022 |
Entered by Super Team from 134.158.195.141 on Wed Oct 26 14:56:19 2022 | | Urgent | Linac Commissionning |
|
camera SST2 HS ? | | Parametres de recipe_recipe_LI_TL_RI_20221014_16_44_34.txt
mais avec Idipole=144 au lieu de
156.7 ...... (je ne comprends pas |
|
|
83
|
Fri Oct 1 15:40:37 2021 |
Entered by Christelle Bruni from 82.64.20.144 on Fri Oct 1 15:40:21 2021 | Fixed | Linac | Linac Commissionning |
|
bilan du premier octobre 2021 | | Bilan
- |
|
|
50
|
Fri Jul 9 14:48:03 2021 |
Entered by Christelle Bruni from 82.64.20.144 on Fri Jul 9 14:47:39 2021 | Fixed | Shift summary | Linac Commissionning |
|
bilan du 9 juillet 2021 | | -Canon
-Ajustement avec
la cathode aluminium fait
-Possibilité |
|