ID Date Authordown Status Type Category Location Title
  29   Thu Oct 21 09:45:03 2021 Manar AmerFixedinfovacuumThomX iglooPressure On mirror Chambers

At 9h30 in the morning, the pressure on the mirror chambers is:

  • on the left                    :  1.6*10^-9 mbar
  • on the right (sortie X)  :  6.5*10^-9 mbar

it appears to have decreased significantly compared to the previous deccend !!!!!!

Manar Amer wrote:

At 10h in the morning, the pressure on the mirror chambers is:

  • on the left                    :  1.9*10^-9 mbar
  • on the right (sortie X)  :  1.0*10^-8 mbar

Bruno mentions that the pressure on the left is descending too slow,  a leakage check to be done on Tomorrow by the vacuum branch.

Manar Amer wrote:

At 15h30 in the afternoon, the pressure on the mirror chambers is:

  • on the left                    :  2.0*10^-9 mbar
  • on the right (sortie X)  :  1.4*10^-8 mbar

the pressure decreased by 0.2 in ~ 5 hours for right , but increased by 0.1 for left

not an accurate reading for the change over time

will need to get the pressure vs time graph from the control room. 

 

Manar Amer wrote:

 

At 10h45 in the morning, the pressure on the mirror chambers is:

  • on the left                  :  1.9*10^-9 mbar
  • on the right (sortie X)  :  1.6*10^-8 mbar

 

 

 

Attachment 1: 21102021_vacuum_pressure_on_mirrorsChambers_9h30.jpg
21102021_vacuum_pressure_on_mirrorsChambers_9h30.jpg
  30   Thu Oct 21 18:31:11 2021 Manar AmerFixedinfovacuumThomX iglooPressure On mirror Chambers Leckage Test

Leakage test done in the afternoon.

The method :

  • an atomic mass spectrometer is connected to the mirror chamber and a measurement is taken to see all the atoms and molecules in the chamber
  • after a Helium gas is spread around the outside of the chamber
  • there is a leak if there is a spike at Helium (4 amu)

Attached is a picture of the spectrometer plot.

Conclusion: No leak in the cavity and the pressure is expected to decrease in the coming days

The pressure now is:

  • on the left                    :  1.6*10^-9 mbar
  • on the right (sortie X)  :  1.4*10^-8 mbar

**Note: there is an increase in the pressure after doing the measurement, which is expected from the spectrometer bumping ions to do the measurement.

 

Manar Amer wrote:

At 9h30 in the morning, the pressure on the mirror chambers is:

  • on the left                    :  1.6*10^-9 mbar
  • on the right (sortie X)  :  6.5*10^-9 mbar

it appears to have decreased significantly compared to the previous deccend !!!!!!

Manar Amer wrote:

At 10h in the morning, the pressure on the mirror chambers is:

  • on the left                    :  1.9*10^-9 mbar
  • on the right (sortie X)  :  1.0*10^-8 mbar

Bruno mentions that the pressure on the left is descending too slow,  a leakage check to be done on Tomorrow by the vacuum branch.

Manar Amer wrote:

At 15h30 in the afternoon, the pressure on the mirror chambers is:

  • on the left                    :  2.0*10^-9 mbar
  • on the right (sortie X)  :  1.4*10^-8 mbar

the pressure decreased by 0.2 in ~ 5 hours for right , but increased by 0.1 for left

not an accurate reading for the change over time

will need to get the pressure vs time graph from the control room. 

 

Manar Amer wrote:

 

At 10h45 in the morning, the pressure on the mirror chambers is:

  • on the left                  :  1.9*10^-9 mbar
  • on the right (sortie X)  :  1.6*10^-8 mbar

 

 

 

 

Attachment 1: 21102021_vacuum_pressure_on_mirrorsChambers_16h30.jpg
21102021_vacuum_pressure_on_mirrorsChambers_16h30.jpg
Attachment 2: 21102121_MassSpectrometerOpticalCav.png
21102121_MassSpectrometerOpticalCav.png
  31   Fri Oct 22 17:36:05 2021 Manar AmerFixedinfovacuumThomX iglooPressure On mirror Chambers Plot

A plot showing the descend of the vacuum in the mirror chambers (data to plot it obtained yesterday evening)

The regions where there is a drastic decrease is when the ionic pump was turned on.

Today in the morning the pressure was

  • on the left                    :  1.3*10^-9 mbar
  • on the right (sortie X)  :  4.9*10^-9 mbar

in the evening the pressure was

  • on the left                    :  1.4*10^-9 mbar
  • on the right (sortie X)  :  4.7*10^-9 mbar

Attachment 1: PressureOverTime.png
PressureOverTime.png
  32   Tue Oct 26 09:20:01 2021 Manar AmerFixedinfovacuumThomX iglooPressure On mirror Chambers Plot

During the weekend 23-24th of October, the lab and ThomX suffered a power breakdown.
All the pumping systems had to restart.

as a consequence, the pressure on Monday 25th morning was 4.3e-9 and 4.6e-9 mbar in the left and right vessels.

this morning, the Tuesday 26th, the pressure is 1.4e-9 and 3e-9 mbar.
now, these pressures are compatible with the opening of the valves!

Manar Amer wrote:

A plot showing the descend of the vacuum in the mirror chambers (data to plot it obtained yesterday evening)

The regions where there is a drastic decrease is when the ionic pump was turned on.

Today in the morning the pressure was

  • on the left                    :  1.3*10^-9 mbar
  • on the right (sortie X)  :  4.9*10^-9 mbar

in the evening the pressure was

  • on the left                    :  1.4*10^-9 mbar
  • on the right (sortie X)  :  4.7*10^-9 mbar

 

  33   Wed Oct 27 09:34:04 2021 Manar AmerFixedinfovacuumThomX iglooPressure On mirror Chambers Plot

Pressure is 1.4e-9 and 2.6e-9 mbar this morning.

Manar Amer wrote:

During the weekend 23-24th of October, the lab and ThomX suffered a power breakdown.
All the pumping systems had to restart.

as a consequence, the pressure on Monday 25th morning was 4.3e-9 and 4.6e-9 mbar in the left and right vessels.

this morning, the Tuesday 26th, the pressure is 1.4e-9 and 3e-9 mbar.
now, these pressures are compatible with the opening of the valves!

Manar Amer wrote:

A plot showing the descend of the vacuum in the mirror chambers (data to plot it obtained yesterday evening)

The regions where there is a drastic decrease is when the ionic pump was turned on.

Today in the morning the pressure was

  • on the left                    :  1.3*10^-9 mbar
  • on the right (sortie X)  :  4.9*10^-9 mbar

in the evening the pressure was

  • on the left                    :  1.4*10^-9 mbar
  • on the right (sortie X)  :  4.7*10^-9 mbar

 

 

  36   Tue Nov 16 15:23:22 2021 Manar AmerFixedreportutilitiesThomX iglooIris Mounts on Cavity Windows

In order to find the Alignment of the ThomX cavity, Yann built mounts that could be placed directly on the windows outside the cavity, where we can place an iris at the center.

The center of the iris on the mount corresponds to the center of the mirror.

4 were made, big one for the injection and 3 small ones for the other windows. 

The big one fits, but the small ones don't fit, as the heads of screws exceed the circle boundary.

A change to them will be done so that they will fit where they will be clipped from the side.

 

Attachment 1: Iris_Mounts_On_Windows.jpg
Iris_Mounts_On_Windows.jpg
Attachment 2: P1_Injection_Mirror_Window_Iris_Mount.jpg
P1_Injection_Mirror_Window_Iris_Mount.jpg
Attachment 3: InkedS3_Mirror_Window_Outside_LI.jpg
InkedS3_Mirror_Window_Outside_LI.jpg
  37   Fri Nov 19 16:33:29 2021 Manar AmerFixedreportutilitiesThomX iglooIris Mounts on Cavity Windows

The new iris mounts fixed on the small cavity windows.

Need additional 2 irises.

Manar Amer wrote:

In order to find the Alignment of the ThomX cavity, Yann built mounts that could be placed directly on the windows outside the cavity, where we can place an iris at the center.

The center of the iris on the mount corresponds to the center of the mirror.

4 were made, big one for the injection and 3 small ones for the other windows. 

The big one fits, but the small ones don't fit, as the heads of screws exceed the circle boundary.

A change to them will be done so that they will fit where they will be clipped from the side.

 

 

Attachment 1: Iris_Mounts_On_small_Windows.png
Iris_Mounts_On_small_Windows.png
Attachment 2: Iris_Mounts_Fixed_On_small_Windows.png
Iris_Mounts_Fixed_On_small_Windows.png
  38   Tue Jan 11 10:32:45 2022 Manar AmerFixedreportlasers and opticsThomX iglooOne Five laser moved

The One Five laser and its controller have been moved from PLIC to ThomX Iglo.

In preparation to Install the Amplifier from Alphanov

  46   Thu Jan 5 10:16:38 2023 Manar AmerFixedinfoutilitiesThomX iglooAlphanov amplifier chiller instruction manual

Adding the instructions manual for the Alphanov Amplifier SMC Chiller

Installation and Maintenance Manual Water Cooled Thermo Con for Rack Mount HECR Series

Attachment 1: HEC-OM-U015-B.pdf
  6   Wed Nov 20 14:52:45 2019 Loïc AmoudryFixedinfolasers and optics | vacuumOptical roomNew valve cabling and 30Hz noise PZT

The Pneumatic valves are still coming back to "close" position.
Now the air bottle is always "open" to keep the valves "open".

The 30Hz noise is still here. We tried to cut off all the air flows. It only decreased the noise intensity but didn't change its shape.

21/11/2019 :

The pneumatic valves are now connected permanently to the university airflow network.
there is a small air leakage but it is not an issue anymore.

the 30Hz noise has been fixed too as it was coming from the extreme position of M1 and M4 (plan mirrors) and due to mechanical instability in this position (motor "outside")

Attachment 1: Noise_with_all_flow_off.png
Noise_with_all_flow_off.png
Attachment 2: Noise_with_room_flow_on.png
Noise_with_room_flow_on.png
Attachment 3: Noise_30Hz.png
Noise_30Hz.png