  Status of commissioning, report also here plots are reports., Page 16 of 24  Not logged in ELOG logo
ID Date Author Status Type Category Location Titledown Text Attachments
  110   Tue Jan 11 10:36:35 2022 Manar AmerFixedreportlasers and opticsThomX iglooFP cavity alignment The alignment is on hold until next week
17th - 18th  Jan

an Alignment attempt will be done
  
  113   Mon Jan 17 21:22:28 2022 Manar AmerFixedreportlasers and opticsThomX iglooFP cavity alignment ***** Continuation of the alignment ----
FP Cavity Open --- ****

The cavity was put under outer
 Interior_of_cavity_P1_S3_windowOpen.jpgInterior_of_cavity_P1_S3_windowOpen_irrisOnP1.jpgCavityAlignment_cavityOpen_S2_Output.jpgCavityAlignment_cavityOpen_S3_Output.jpeg 
  114   Wed Jan 19 09:36:53 2022 Manar AmerFixedreportlasers and opticsThomX iglooFP cavity alignment Yesterday, we did the alignment again using
Iris and beam profilers to obtain a more
precise result.
  
  115   Tue Feb 1 14:17:02 2022 Manar AmerFixedreportlasers and optics | detectors and electronicsThomX iglooFP cavity alignment Installed and inputs: 


CW laser ; power = 101
mW
PDH ;

at output

Low
 ThomX_FP_setup_01-02-2022.pngtek0002.png 
  116   Tue Feb 1 16:40:06 2022 Manar AmerFixedreportlasers and optics | detectors and electronicsThomX iglooFP cavity alignment This afternoon, I did some alignment of
the injection mirrors with a fast scan on
the LaseLock to get a regular transmission
  
  117   Wed Feb 2 11:22:51 2022 Manar AmerFixedreportlasers and optics | detectors and electronicsThomX iglooFP cavity alignment This morning with Manar, we installed the
AOM+RF amplifier and the associated fast
feedback loop.
  
  118   Wed Feb 2 11:41:01 2022 Manar AmerFixedreportlasers and optics | detectors and electronicsThomX iglooFP cavity alignment Adding Oscilloscope images


delocked + locked intervals
showing the 20% coupling
lock
 tek0003.pngtek0006.pngtek0007.png 
  119   Thu Feb 3 13:56:24 2022 Manar AmerFixedreportlasers and optics | detectors and electronicsThomX iglooFP cavity alignment Ending alignment series !!




  
  120   Thu Feb 3 14:10:08 2022 Manar AmerFixedreportlasers and optics | detectors and electronicsThomX iglooFP cavity alignment As it can be seen on the first plot, even
with a good locking (good reduction of "high"
frequencies noise: we had better locking
  
  123   Thu Feb 3 18:40:04 2022 Manar AmerFixedreportlasers and optics | detectors and electronicsThomX iglooFP cavity alignment The fluctuation problem has been solved.
It was simply the new scheme to inject
2 RF frequencies in a single EOM.
  
  106   Thu Nov 4 13:05:49 2021 Ronic ChicheFixedinfolasers and opticsThomX iglooFP cavity alignmentas the iris used to locate the FP-cavity
axis have been removed before moving the
table inside the Igloo, we have to find again
  
  107   Thu Nov 4 18:57:16 2021 Ronic ChicheFixedinfolasers and opticsThomX iglooFP cavity alignmentThis afternoon, we continued the alignment
of the red laser.
we did it using the 2 final injection
  
  108   Fri Nov 26 20:12:10 2021 Ronic ChicheFixedreportlasers and opticsThomX iglooFP cavity alignmentA continuation of the alignment process
was done, there was change in it due to variation
in temperature, 
  
  207   Tue Apr 11 16:58:16 2023 Manar AmerFixedreportlasers and optics | detectors and electronicsThomX iglooFP Finesse measurement using CWThis morning, with Ronic and Daniele, we
locked the cavity again (The lock was relatively
easy and stable during the reading of the
 20230411_first_Finesse_reading.JPG20230411_second_Finesse_reading.JPG20230411_Beam_Profile_position_differance_when_changing_FSR.JPG 
  10   Mon Nov 26 15:18:49 2018 Ronic ChicheFixedinfovacuumOptical roomEtuvage cavité THOMXMail de Bruno Mercier
du 19/11/2018 :


Une première cavité
  
  235   Tue Sep 5 18:08:39 2023 Ronic ChicheFixedinfolasers and opticsThomX iglooEquipments shutdownon the August 30rd and 31th, a global power
shutdown was forseen for ThomX.

to prevent damage on equipments,
  
  11   Fri Dec 21 13:55:09 2018 Loïc AmoudryFixedinfovacuumOptical roomEnd of vacuum test and cavity ready for cleaningVacuum tests finished on 19 december
2018.

Spent last two days to discuss
 IMG_20181221_1110152.jpgIMG_20181221_1119082.jpgIMG_20181221_1113122.jpgIMG_20181221_1124492.jpg 
  13   Fri Feb 1 13:20:47 2019 Loïc AmoudryFixedreportutilitiesOptical roomEnd of cleaning, plastic fixed on cavity08/02/19 - End of the cleaning process.  covered_by_plastic.pngcovered_by_plastic2.png 
  415   Wed Mar 5 13:17:26 2025 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooElectrons-Photons phase stability measurementwe installed a measurement at the IP with
the BPM for ion cleaning for electrons and
we used a fast photodiode at the output of
 img1(1).jpg 
  416   Wed Mar 5 15:08:38 2025 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooElectrons-Photons phase stability measurementthe phase between the 500Mhz ring RF oscillator
and the electrons is measured on a BPM and
is very stable after 2-3ms (<< 6ps,
  