  364   Tue Sep 17 12:48:13 2024 Ronic ChicheFixedinfomechanicsThomX iglooFinding correct motors position and parameters to keep the lock during a movethis morning with Daniele, we did a quite
long run with this motor position and it
seems we don't lose the lock too much.
  
  70   Wed Oct 9 10:16:24 2019 Loïc AmoudryFixedinfolasers and opticsOptical roomFiber injection and onefive output powerFiber injection is finished with the new
ThomX stretching CVBG in double pass (+50%
injection power compared to K-BOX CVBG in
  
  237   Wed Sep 6 19:57:48 2023 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFast feedback loop between laser and FP cavitytoday, we tried to lock the FP cavity with
the Smaract motors ON (with option -LV).
we know the Smaract controllers produce
  
  240   Thu Sep 7 19:23:36 2023 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFast feedback loop between laser and FP cavitytoday, after the several unsuccessful attempt
yesterday to get an improvement in the lock,
we decided to "rebuild"
 20230907_182412.jpg20230907_182442.jpg 
  260   Fri Sep 15 18:27:24 2023 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFast feedback loop between laser and FP cavitythis afternoon, we tried to better understand
how to drive properly the EOM to kill high
frequency noise.
  
  267   Wed Sep 20 19:12:16 2023 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFast feedback loop between laser and FP cavityI copy the post about Fast Feedback loop
: https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/265

This morning,
  
  332   Tue Mar 19 13:01:22 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFP-cavity lock survey during the Linac section changing operationThis morning with Daniele, we operated
the FP-cavity to be sure there is no issue
due to the Linac section changing operation
  
  333   Tue Mar 26 10:20:54 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFP-cavity lock survey during the Linac section changing operationThis morning, I locked again the FP-cavity
at more than 50kW with 33% of laser amplifier
ratio.
  
  335   Tue Apr 2 09:19:31 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFP-cavity lock survey during the Linac section changing operationfrom now on, the transmission factor for
calculating the FP intra cavity power is
1/1.75ppm ~ 570 000 (changed in the Powermeter
  
  336   Tue Apr 9 09:38:18 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFP-cavity lock survey during the Linac section changing operationthis morning, I had to restart the chiller.
Temp Amp 1 is at 27.5°C after having
started the amplifier at 33% ratio.
  
  337   Thu Apr 11 09:58:10 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFP-cavity lock survey during the Linac section changing operationthis morning, the computer was restarted
and I had to launch all the applications.
no problem except the powermeter for
 Capture.JPG 
  338   Thu Apr 25 09:09:49 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFP-cavity lock survey during the Linac section changing operation

this morning, the chiller was in
error and I had to restart it.
  
  339   Tue May 14 09:20:27 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFP-cavity lock survey during the Linac section changing operationYesterday, the ThomX water circuit should
have been repared,
and yesterday aftenoon, Daniele restarted
  
  340   Tue May 14 10:37:41 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFP-cavity lock survey during the Linac section changing operationthe air temperature is between 21°C
and 22°C.

I tried to lock the cavity but
 Capture.JPG 
  341   Tue May 28 15:05:46 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFP-cavity lock survey during the Linac section changing operationtoday, I tried to restart the amplifier
at 0% (without 3rd stage) but it didn't
start... still the same error message.
  
  342   Fri May 31 18:12:59 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFP-cavity lock survey during the Linac section changing operationtoday with Daniele, we disconnected the
EOM to increase the injected power of the
amplifier, we were at 4.8mW but we still
  
  300   Thu Nov 30 12:33:08 2023 Ronic ChicheFixedinfolasers and opticsThomX iglooFP-cavity inside power sensitivitythis morning I monitored the frequency
shift between the FP-cavity frequency (the
laser is locked on it) and the RF reference
 FP-cavity_freq.pngScreenshot_2023-11-30_12-30-23.png 
  236   Tue Sep 5 18:21:12 2023 Ronic ChicheFixedinfolasers and opticsThomX iglooFP-cavity FSR shifttoday, to match the ring frequency at 500.25MHz
(15th laser harmonic), we did a frequency
shift on the laser using the Smaract motors
 20230905_173506.jpg 
  128   Fri Mar 11 12:46:58 2022 Ronic ChicheFixedinfolasers and opticsThomX iglooFP cavity mode axis change and Finesse measurementthis morning with Manar, we did a cavity
mode axis change.

we checked the cavity mode centroid
  
  109   Thu Dec 2 21:31:21 2021 Manar AmerFixedreportlasers and opticsThomX iglooFP cavity alignment Note the direction of injection is  
  M1 - M2 - M3 - M4

                                                      
 2021_12_02_M2_Transmission.jpg2021_12_02_M3_transmission_90deg.PNG 