  Status of commissioning, report also here plots are reports., Page 15 of 23  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Status Type Category Location Title Text Attachments
  176   Thu Jan 5 09:58:50 2023 Ronic ChicheFixedinfolasers and opticsThomX iglooAlphanov amplifier beam profile measurementyesterday morning with Manar,

1) we fixed the threshold level
of the laser input signal which makes the
 Tutoriel_PD_PULS.pdf2023_Alphanov_Beam_Profile_setup.jpg 
  175   Mon Jan 2 15:21:09 2023 Ronic ChicheFixedinfolasers and opticsThomX iglooAlphanov amplifier beam profile measurementtoday with Manar, we brought everything
to make the profile measurement.

the chiller was in error
  
  174   Thu Dec 15 11:41:36 2022 Ronic ChicheFixedissuelasers and opticsThomX iglooAlphanov amplifier issueYesterday, we received the controller back
from Alphanov
and I tested it immediately in the
  
  173   Tue Dec 6 11:47:36 2022 Ronic ChicheFixedissuelasers and opticsThomX iglooAlphanov amplifier issueToday, I did a Teams meeting with Guillaume.
He didn't see any problem with
the controller.
 Sécurité_et_CC_ampli_Alphanov.pdf 
  172   Thu Dec 1 13:51:05 2022 Ronic ChicheFixedissuelasers and opticsThomX iglooAlphanov amplifier issueThe laser amplifier controller has been
sent yesterday and received today by Alphannov.

they should do the assessment quickly...
  
  171   Wed Nov 9 14:49:52 2022 Ronic ChicheFixedissuelasers and opticsThomX iglooAlphanov amplifier issueI just tested the fuse inside the black
ON/OFF switch on the rear panel => it
is OK ! :-(
  
  170   Wed Nov 9 13:03:50 2022 Ronic ChicheFixedissuelasers and opticsThomX iglooAlphanov amplifier issueon Monday morning 7/11, we tried to restart
the Alphanov amplifier which was not turned
on since end of april 2022, but it didn't
  
  169   Wed Nov 9 11:34:54 2022 Ronic ChicheFixedinfolasers and opticsThomX iglooStrecher and fiber injection alignmentMonday 7/11 morning, the power in the fiber
was still 6.2 mW

  
  168   Thu Nov 3 09:09:18 2022 Ronic ChicheFixedinfolasers and opticsThomX iglooStrecher and fiber injection alignmentthis morning : still 6.2 mW at the output
of the fiber.

the powermeter has been removed
  
  167   Wed Nov 2 11:42:43 2022 Ronic ChicheFixedinfolasers and opticsThomX iglooStrecher and fiber injection alignmentThis morning with Manar, we continued the
strecher CVBG alignment and fiber injection
procedure :
  
  166   Mon Oct 24 17:35:01 2022 Ronic ChicheFixedinfolasers and opticsThomX iglooStrecher and fiber injection alignmentManar + Victor, today in the morning we
aligned the CVBG of the stretcher.

The double path using the mirror
  
  165   Thu Oct 20 15:01:02 2022 Ronic ChicheFixedinfolasers and opticsThomX iglooStrecher and fiber injection alignmentI used the 33MHz spectrum measurement :
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/153
fitted by P=P0*sech²((f-f0)/df)
 D24-02.xls33MHz_power_spectrum_after_double_patch_strecher_CVBG.png 
  164   Wed Oct 19 15:01:32 2022 Ronic ChicheFixedinfolasers and opticsThomX iglooStrecher and fiber injection alignmentThis morning with Ronic, using a pickup
mirror, we measured the power in different
locations along the path of the stretcher
  
  163   Wed Oct 19 14:57:43 2022 Ronic ChicheFixedinfolasers and opticsThomX iglooStrecher and fiber injection alignmentThis morning with Manar, we measured the
power at different points:
- direct measurement at the output
  
  162   Tue Oct 18 17:51:12 2022 Ronic ChicheFixedinfolasers and opticsThomX iglooStrecher and fiber injection alignmentIn preparation for tomorrow morning, I
did a test with a 45° mount to have a
power pickup inside the injection box.
  
  161   Mon Oct 17 13:58:08 2022 Ronic ChicheFixedinfolasers and opticsThomX iglooStrecher and fiber injection alignmentThis morning with Viktor, we started the
alignment of the CVBG and fiber.

we did a better alignment of the
 Adjustment_SMS.pdf 
  160   Thu Oct 13 12:26:07 2022 Ronic ChicheFixedinfolasers and opticsThomX iglooStrecher and fiber injection alignmentToday, after laser was modelocked, we checked
the power inside the fiber coming from the
Alphanov Strecher box.
  
  159   Thu Oct 13 12:19:11 2022 Ronic ChicheFixedinfolasers and opticsOptical room33MHz laser SN2439 back to OrsayToday, we succeded to make the laser modelock.
the ouptut power is above 35mW (the
powermeter was saturated)
 IMG_20221013_095839.jpg 
  158   Thu Oct 13 12:12:49 2022 Ronic ChicheFixedinfolasers and opticsOptical room33MHz laser SN2439 back to OrsayYesterday, we put back the 33MHz oscillator
into the casemate with the new Smaract controller.
after switching ON the laser controller,
  
  157   Fri Oct 7 17:47:39 2022 Ronic ChicheFixedinfolasers and opticsOptical room33MHz laser SN2439 back to OrsayToday, we used an "ELI-NP" Smaract
controller made with these 2 references :
MCS-3CC-ETH-TAB (SN 2271) => main
  