  Status of commissioning, report also here plots are reports., Page 5 of 5  Not logged in ELOG logo
ID Date Author Status Type Category Location Title Text Attachments
  9   Thu Apr 29 06:14:09 2021 Manar AmerFixedreportlasers and opticsOtherMode observed and cavity Lock ** Following up from yesterday an observation
about the TM00 mode : it has been seen with
similar dimensions and its position is the
 20212804_Fundamental_mode_in_cavity_2D_-_Position.png20212804_Cavity_Coupling_with_Koheras.jpg20212804_Temperature_Curve.jpg 
  8   Tue Apr 27 13:57:15 2021 Manar AmerFixedreportlasers and opticsOtherAlignment using Koheras Following the Helium Neon Alignment + change
in the distance between the mirrors to be;
M3-M4 = 90.5 mm , M1-M2 = 80.2 mm  -→
 6x 
  7   Mon Apr 19 19:11:47 2021 Manar AmerFixedreportmechanics | softwareOtherDistances between mirrors
  At the reference zero the
distance between the mirrors is (taken from
a reference presentation "status9nov2020"
 20211604__Distances_Between_mirrors.pngstatus9nov2020.pptx 
  6   Mon Apr 19 18:47:28 2021 Manar AmerFixedreportlasers and opticsOtherAlignment using Helium Neon Laser 05 April  2021 :  A rough alignment
of the cavity was done using the Helium Neon
Laser.
 20210202__Helium_Neon_laser_parameters.jpg 
  5   Mon Apr 19 18:41:03 2021 Manar AmerFixedreportmechanics | cabling | softwareOtherSetting up the MotorsA document attached that describes the
procedure needed to:

- connect the motors
 setting_up_the_motors.docx 
  4   Thu Apr 15 19:54:19 2021 Manar AmerFixedreportmechanics | cablingOtherMirrors Mottors Connections Added the cabling to the categories 




  
  3   Thu Apr 15 19:45:08 2021 Manar AmerFixedreportmechanicsOtherMirrors Mottors Connections * The connections to control the motors
of the mirrors are connected in the order
stated :
 20210804_Motor_connections_with_mirrors_inside_cavity_box.jpg20210804_Mottor_cables_behind_cavity_box.jpg 
  2   Tue Apr 6 09:25:47 2021 Ronic ChicheFixedinfolasers and optics | detectors and electronicsOptical roomPhase noise measurement of the Amplitude MIKANCoupling into a 50-50% fiber coupler using
the Thorlabs XYZ table NanoMax TS.
We reached 117mW after the 50% arm
  
  1   Tue Mar 23 18:33:16 2021 Ronic ChicheFixedinfolasers and optics | detectors and electronicsOptical roomPhase noise measurement of the Amplitude MIKANInstallation of the MIKAN.
powermeter (with OD1) just after the
oscillator shows 440mW for 4A of the MIKAN
  