Laser Interaction
Notes concernant le laser Interaction, Page 1 of 2
Not logged in
Find
|
Last day
|
Login
|
Help
Full
| Summary |
Threaded
21 Entries
Goto page 1,
2
Next
All
ID
Date
Author
Status
Type
Category
Important
Subject
Icon
Text
21
Fri May 23 00:33:10 2025
Kilperic - MJ - KD
Fix
Detection
Correspondance Position centre ouverture FENTES 2 vs HEXA_Echantillon
- Bille positionnee sur le 2eme trou en
amont du centre de l'hexa (2eme trou
vers IP)
20
Wed Apr 12 12:05:53 2023
Manar Amer
Under Process
Info
Allignement
Alignment
Morning intervintion for FP : telescope
alignment
continue in the afternoon
19
Tue Apr 11 11:38:10 2023
Manar Amer
Fixed
Info
Other
Cavity Finesse Measurement
This morning FP cavity intervintion : Alignment
and Finesse Measurement
18
Thu Apr 6 13:38:46 2023
Manar Amer
Fixed
Fix
Other
Cavity Lock
This morning FP cavity intervintion and
cavity was locked using CW laser but not
on the fundamental mode.
17
Tue Apr 4 12:16:29 2023
Manar Amer
Fixed
Info
Allignement
FP cavity Alignment
10h00 : Cavity alignment and telescope
installation using CW laser
12h00 : Images of the transmitted
16
Thu Nov 3 10:22:37 2022
Manar Amer
Fixed
Info
Allignement
RE: Stretcher Alignement
now, we have 6.2 mW at output of the strecher
CVBG + injection fiber output.
it's enough to start the laser
15
Mon Oct 24 11:57:36 2022
Manar Amer
Under Process
Info
Allignement
Stretcher Alignement
Fabry Perrot Cavity intervention Manar
+ Victor
Alignment of the stretcher , power
14
Fri Oct 21 20:01:39 2022
Entered by Marie Jacquet from 134.158.205.42 on Fri Oct 21 20:01:22 2022
Question
Detection
bruit diode fluo et det diode
Le debut du elog "ring commissioning"
d'aujourd'hui c'est ca :
8H15 demarrage
13
Thu Sep 29 16:49:50 2022
Entered by Marie Jacquet from 134.158.89.45 on Thu Sep 29 16:49:38 2022
Info
Detection
Table 1 mise en position faisceau
vers 16h30 aujourd'hui
Pas touche aux entrees du AH401
Draft
Thu Sep 29 16:46:31 2022
Entered by Marie Jacquet from 134.158.89.45 on Thu Sep 29 16:46:15 2022
Detection
, entered from 134.158.89.45
11
Mon Feb 21 14:10:37 2022
Entered by Super Team from 134.158.195.141 on Mon Feb 21 14:10:19 2022
Fixed
Info
Detection
installation Pico3 AH501D
Le pico3 a été installé
dans la casemate. Il est branché en
baie 11. Il n'y a que la voie 1 qui connectée
10
Thu Feb 3 18:30:57 2022
Entered by Super Team from 134.158.195.141 on Thu Feb 3 18:30:43 2022
Fixed
Info
Allignement
Measurement of the Finesse of FP Cavity
Manar and Ronic, end of day on the intervention
of FP cavity
noise on the transmitted signal
9
Thu Feb 3 13:05:03 2022
Entered by Super Team from 134.158.195.141 on Thu Feb 3 13:04:50 2022
Fixed
Info
Allignement
intervention FP
Work on the FP cavity to improve coupling.
8
Wed Feb 2 10:45:04 2022
Entered by Christelle Bruni from 134.158.195.142 on Wed Feb 2 10:44:50 2022
Fixed
Info
Allignement
Alignement cavité Fabry perrot ce
matin 9h-10h
7
Tue Jan 18 17:24:26 2022
Ronic
Fixed
Info
Allignement
RE: Alignement cavité FP
Aujourd'hui nous nous sommes aperçu
que le précédent alignement
n'était pas assez précis
6
Tue Jan 18 09:19:22 2022
Ronic
Not Fixed
Info
Allignement
Alignement cavité FP
Hier avec Viktor et Manar nous avons ouvert
la cavité FP et appliqué la
procédure d'alignement qui consiste
5
Thu Jan 13 09:31:25 2022
Entered by Aurelien Martens from 134.158.88.183 on Thu Jan 13 09:31:06 2022
Info
Allignement
status of interaction laser amplifier
Yesterday (12th) Alphanov finished alignment
of stretcher and compressor of the laser
amplifier. Due to dropping water in water
4
Wed Jan 12 09:25:10 2022
Entered by Aurelien Martens from 134.158.88.183 on Wed Jan 12 09:24:13 2022
Info
Allignement
intervention Alphanov (ampli laser)
Alphanov continue l'intallation de
l'ampli laser interaction aujourd'hui.
3
Tue Jan 11 15:00:07 2022
Entered by Super Team from 134.158.195.141 on Tue Jan 11 14:59:49 2022
Under Process
Info
Allignement
installation laser et ampli Alphannov
intervention sur CFP pour installation
laser et ampli avec Alphannov debute a 10h30
(AM, RC, + Alphannov)
2
Tue Mar 2 15:00:20 2021
Entered by Hugues Monard from 134.158.195.143 on Tue Mar 2 14:59:56 2021
Under Process
Fix
Hardware issue
intervention Microplan polissage marbre ligne X
intervention Microplan + Institut Neel
: polissage marbre ligne X du 1 au
5 mars 2021, montage du transfocateur sur
Goto page 1,
2
Next
All