  Toutes les notes concernant les Commissionning de ThomX, Page 55 of 63  Not logged in ThomX    logo
Entry   cb/ hg/sc/jnc; run du 29 nov 2022 
Entry   Entered by Marie Jacquet from 134.158.89.45 on Wed Dec 7 11:39:09 2022; Dipole extraction : signe du courant a mettre 
Entry   Entered by Marie Jacquet from 134.158.89.45 on Wed Dec 7 14:17:27 2022; realignement 1er doublet de dipole 
Entry   Entered by Super Team from 134.158.195.142 on Wed Dec 7 16:58:42 2022; Linac measurements @ différent modulator voltage settings  
Entry   MJ HG KD; LE passee ce soir faisceau sur yag 5 Faisceau_dans_la_LE_2022-12-09_18-36-53.png
Entry   SC/MJ; Linac + TL divers yag_TL2.pngBPM_LI.png
Entry   HG/CB/KD; run du 14 décembre 2022 
Entry   Entered by Maher OMEICH from 134.158.91.212 on Tue Jan 3 17:05:44 2023;  
Entry   SC/ND/IC/VK/VM; Faisceau  11x
Entry   JNC/HG/CB; reprise soirée --> non fonctionnel 
Entry   SC/MJ/VC; run du 14 février 2023 _ redémarrage 
Entry   CB/HG/JNC; suite run 14/02/2023 
icon14.gif   BM/NE/JNC; passage TL MPS 
Entry   JNC/CB; run du 15 février 2023 10x
Entry   MJ SC;  Screenshot_from_2023-02-16_15-48-39.pngScreenshot_from_2023-02-16_16-01-46.pngScreenshot_from_2023-02-16_16-18-55.png
Entry   JNC/CB/HG; démarrage 17/02/2023, urgent pb LI SST1, TL SST1  TLSST_statusScreenshot_from_2023-02-17_12-10-53.png
Entry   JNC/CB; run de 17/02/2023 
Entry   Entered by Marie Jacquet from 134.158.205.50 on Sat Feb 18 14:37:01 2023; Comparaisons mesures-simuls ASTRA versus I_Soleno - Complements elog 676 et 681 2023-02-18-elog.pdf
Entry   CB/JNC; run du 27 février 2023 
Entry   CB/JNC/MJ/ VK/VM; run du 1er mars 2023 Screenshot_2023-03-01_at_19.27.13.pngScreenshot_2023-03-01_at_19.26.29.png