103
|
Mon Oct 11 11:09:35 2021 |
Entered by SC, HG et MO from 134.158.195.142 on Mon Oct 11 11:09:19 2021 | Under Process | Problem | Linac Commissionning |
|
Alarme anoxie | | Démarrage ce matin, SC, MO et HG.
AM pour les BPMs, VS pour le laser, ME pour
le commissioning et EG pour l'alignement |
|
|
351
|
Fri Feb 18 13:24:30 2022 |
Entered by HM/SC from 134.158.195.141 on Fri Feb 18 13:24:16 2022 | Under Process | Linac | Linac Commissionning |
|
Alarme anoxie | | Modulateur repassé sur off le temps
du déjeuner, problème d'eau
Pas d'autorisation du PSS, |
|
|
271
|
Thu Jan 20 17:16:43 2022 |
Entered by Super Team from 134.158.195.142 on Thu Jan 20 17:16:30 2022 | Under Process | Info | Vide |
|
Acces controlé casemate | | Acces controlé pour Mercier, G.
Mercadier, et D. Grasset à 17h. (pour
30 min) |
|
|
Draft
|
Mon Feb 17 11:00:01 2025 |
VM, IC, VK | Under Process | Shift summary | |
|
70 MeV WP | | 10h30 Start beam
Since Friday evening the problem
to store the beam at 70 MeV. There is 1 turn |
|
|
977
|
Tue Dec 10 11:35:16 2024 |
VM,HG,SC | Under Process | Shift summary | LI | TL | LE | Ring | Linac Commissionning | Ring Commissioning |
|
50 and 70 MeV Emittance, and transport | | Intervention chiller (Maher) : maintenance
nécessaire à prévoir
(clé outil clignote) |
 |
|
1167
|
Thu Dec 11 08:38:30 2025 |
VM, IC | Under Process | Shift summary | Diag | Ring Commissioning |
|
40 MeV operation | | 8h37 Warm-up ThomX: Modulator, Laser, Fridge
8h44 Chillers were started, cycling
all magnets. |
12x |
|
1024
|
Fri Feb 28 00:32:21 2025 |
Entered by Marie Jacquet from 134.158.205.38 on Thu Feb 27 23:45:19 2025 | | Shift summary | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
27 fevrier (visite Alberto Paola Luca) | | ** Nouvelle
prise d'images pour determiner les distortions
du det : |
|
|
1022
|
Wed Feb 26 22:52:03 2025 |
Entered by Marie Jacquet from 88.165.97.136 on Wed Feb 26 22:50:49 2025 | | Shift summary | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
26 fevrier (visite Alberto Paola Luca) - Detecteur Photonic Science | | Suite du commissioning
det Photonic Science
** |
|
|
1199
|
Wed Feb 25 07:29:16 2026 |
KD MJ DN VK IC | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
25 fevrier 2026 - Alignement TRANSFO - Prise d'images PhotonicScience Rack transfo IN/OUT | | 7h30: mise en chauffe en remote (frigo/chillers,
laser, modulateur, cyclage)
*** |
|
|
1020
|
Tue Feb 25 22:59:57 2025 |
Entered by Marie Jacquet from 88.165.97.136 on Tue Feb 25 22:59:29 2025 | | Shift summary | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
24 -25 fevrier (visite Alberto Paola Luca) - Detecteur Photonic Science | | Commissioning det Photonic Science
** Depose
Dectris, mise en place Photonic, alignement |
|
|
1045
|
Fri Mar 21 17:57:40 2025 |
Entered by Marie Jacquet from 134.158.89.45 on Fri Mar 21 17:57:25 2025 | | Shift summary | Linac Commissionning | Ring Commissioning |
|
21 mars - Mesures X-rays - Bravin & co | | Det
Photonic fond de la X-hutch
Tomo : un |
|
|
1087
|
Wed Jun 11 08:46:58 2025 |
Entered by Marie Jacquet from 134.158.205.17 on Wed Jun 11 08:46:44 2025 | | Shift summary | LI | Ring |
|
2025-06-04 Fluo-spectro : Spectre du 2025-06-04 | | |
|
|
1223
|
Wed Apr 1 07:45:03 2026 |
KD MJ RC DN VK | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
1e avril 2026 - Scan Energy-Angle 61.5 MeV | | 7h40 : mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)
==> SF6 à remplir avant |
|
|
1042
|
Thu Mar 20 18:41:55 2025 |
Entered by Marie Jacquet from 134.158.205.16 on Thu Mar 20 18:41:39 2025 | | Shift summary | LI | Ring | Linac Commissionning | Ring Commissioning |
|
19 et 20 mars - Mesures X-rays - Bravin & co | | 19
mars 2025
|
|
|
137
|
Thu Oct 28 16:40:39 2021 |
Entered by sophie chance from 134.158.195.141 on Thu Oct 28 16:40:25 2021 | Under Process | Linac | Linac Commissionning |
|
10 Hz | | Passage à 10 Hz, Augmentation progressive
de la bobine
Attenuation canon à 3 dB |
|
|
Draft
|
Tue Jan 18 11:57:15 2022 |
Entered by Hayg Guler from 134.158.91.29 on Tue Jan 18 11:44:00 2022 | | | |
|
, entered from 134.158.91.29 | | |
|
|
Draft
|
Thu Sep 22 10:08:30 2022 |
Entered by Hayg Guler from 134.158.91.29 on Thu Sep 22 10:08:17 2022 | Fixed | | |
|
, entered from 134.158.91.29 | | |
|
|
Draft
|
Thu Jul 1 10:12:11 2021 |
Entered by Nicolas Delerue from 134.158.89.243 on Thu Jul 1 10:11:03 2021 | Not Fixed | | |
|
, entered from 134.158.89.243 | | |
|
|
Draft
|
Mon Oct 25 19:23:51 2021 |
Entered by Super Team from 134.158.195.142 on Mon Oct 25 19:23:35 2021 | | | |
|
, entered from 134.158.195.142 | | Passage de la sect |
|
|
Draft
|
Tue Apr 4 15:21:51 2023 |
| | | |
|
, entered from 134.158.195.141 | | <p>12h10: Mise en chauffe modulateur, laser
et chiller + PA</p>
|
|