197
|
Thu Dec 2 10:38:44 2021 |
Entered by Maher OMEICH from 134.158.91.212 on Thu Dec 2 10:38:07 2021 | | Anneau | Aimants |
|
intervention Soleil | | Bonjour, Patrick Alexandre et Didier Muller
( Soleil ) viendrons demain Vendredi 03/12
toute l'après midi, j'aurai |
|
|
196
|
Wed Dec 1 13:05:53 2021 |
Entered by Super Team from 134.158.195.141 on Wed Dec 1 13:04:57 2021 | Under Process | Linac | Linac Commissionning |
|
Alignements tete de machine | | Conditions
Phase RF :
On
se place à la phase qui maximise l'energie
des électrons. |
 |
|
195
|
Wed Dec 1 11:45:03 2021 |
Entered by Super Team from 134.158.195.141 on Wed Dec 1 11:44:50 2021 | Under Process | Linac | Laser | Linac Commissionning |
|
alignement laser | | Laser:
Recentrer le faisceau
laser dans la mire en agissant sur les moteurs
M5. |
 |
|
194
|
Tue Nov 30 17:11:41 2021 |
Entered by Moutardier Alexandre from 134.158.195.144 on Tue Nov 30 17:11:17 2021 | Fixed | Problem | CC |
|
Problème pc client2 | | Le client 2 a freeze.
Il était impossible de fermer
les intefaces ouverte, d'ouvrir un nouveau |
|
|
193
|
Tue Nov 30 11:52:44 2021 |
Entered by Maher OMEICH from 134.158.91.212 on Tue Nov 30 11:52:02 2021 | Not Fixed | Problem | Linac Commissionning |
|
| | Après avoir exécuter des
opérations demandées par mon
interlocuteur de Scandinova pour remédier |
|
|
192
|
Tue Nov 30 10:31:04 2021 |
Entered by Super Team from 134.158.195.141 on Tue Nov 30 10:30:47 2021 | Not Fixed | Problem | RF D1 | Linac Commissionning |
|
Soucis modulateur | | problèmes pour démarrer,
il se met encore en défait pendant
la periode de chauffe. Le probleme vu hier |
|
|
191
|
Mon Nov 29 15:24:31 2021 |
Entered by Super Team from 134.158.195.142 on Mon Nov 29 15:15:42 2021 | Under Process | Shift summary | Linac Commissionning |
|
run du 29 novembre 2021 | | HG et CB
valeur de départ M5 -1.39,
-0.16 |
  |
|
190
|
Mon Nov 29 10:18:01 2021 |
Entered by Maher OMEICH from 134.158.91.212 on Mon Nov 29 10:17:44 2021 | Not Fixed | Problem | Linac Commissionning |
|
| | Ce matin j'ai eu plusieurs interlock
modulateur
Maher |
|
|
189
|
Fri Nov 26 15:37:56 2021 |
Entered by sophie chance from 134.158.206.40 on Fri Nov 26 15:37:41 2021 | Fixed | Info | Linac Commissionning |
|
CR Reunion planning Linac ThomX | | BILAN DE LA SEMAINE ECOULEE
Mesure stabilité laser en
début de semaine en pointé, |
|
|
188
|
Thu Nov 25 17:07:29 2021 |
Entered by Super Team from 134.158.195.142 on Thu Nov 25 17:07:16 2021 | Fixed | Linac | Linac Commissionning |
|
Contrôle terminé | | |
|
|
187
|
Thu Nov 25 16:04:53 2021 |
Entered by Super Team from 134.158.195.142 on Thu Nov 25 16:04:39 2021 | Under Process | Linac | Linac Commissionning |
|
arret d'urgence | | Tests d'arret d'urgence dans la
casemate |
|
|
186
|
Thu Nov 25 15:55:17 2021 |
Entered by Super Team from 134.158.195.142 on Thu Nov 25 15:54:59 2021 | Under Process | Linac | Linac Commissionning |
|
Test arret urgence faisceau | | |
|
|
185
|
Thu Nov 25 15:01:54 2021 |
Entered by Super Team from 134.158.195.142 on Thu Nov 25 15:01:41 2021 | Under Process | Linac | Linac Commissionning |
|
Contrôle Radioprotection | | Les controles radioprotection ont commencé
vers 14h50
Paramètres faisceau : 100 |
|
|
184
|
Thu Nov 25 11:19:26 2021 |
Entered by Super Team from 134.158.195.142 on Thu Nov 25 11:19:08 2021 | Fixed | Linac | Linac Commissionning |
|
Mesure energie | | Energie avec 2 dB section, 100 pC transport
ok |
|
|
183
|
Thu Nov 25 11:10:49 2021 |
Entered by Super Team from 134.158.195.142 on Thu Nov 25 11:09:21 2021 | Fixed | Linac | Linac Commissionning |
|
Mesure energie | | Mesure avec charge 100pC |
|
|
182
|
Thu Nov 25 10:52:26 2021 |
Entered by Super Team from 134.158.195.142 on Thu Nov 25 10:52:12 2021 | Under Process | Linac | Linac Commissionning |
|
Transport | | Optimisation charge et transport. Charge
100 pC ok.
Optimisation phase canon faite |
|
|
181
|
Thu Nov 25 10:07:23 2021 |
Entered by Super Team from 134.158.195.142 on Thu Nov 25 10:07:10 2021 | Fixed | Linac | Linac Commissionning |
|
Laser | | Réglages laser terminés,
117 uJ en sortie , 50 uJ sur la photocathode.
Le hublot est resté |
|
|
180
|
Thu Nov 25 09:24:52 2021 |
Entered by Super Team from 134.158.195.142 on Thu Nov 25 09:24:38 2021 | Under Process | Linac | Linac Commissionning |
|
Démarrage | | Démarrage modulateur
Viktor aligne le laser, acces en
zone controlée pour ne pas casser |
|
|
179
|
Wed Nov 24 16:52:29 2021 |
Entered by Super Team from 134.158.195.141 on Wed Nov 24 16:52:10 2021 | Under Process | Linac | Linac Commissionning |
|
Mesure d'energie | | Calibration Ecran TL-SST01
|
|
|
178
|
Wed Nov 24 11:21:41 2021 |
Entered by Super Team from 134.158.195.141 on Wed Nov 24 11:21:24 2021 | Under Process | Linac | Laser | Linac Commissionning |
|
shift du 24 Novembre 2021 | | Laser :
Viktor a remis
le hublot pour gagner en stabilité
laser
Energie laser : 54 µJ
laser |
  |