Entry   Entered by Maher OMEICH from 134.158.91.212 on Mon Nov 29 10:17:44 2021;  
Entry   Entered by sophie chance from 134.158.206.40 on Fri Nov 26 15:37:41 2021; CR Reunion planning Linac ThomX Réunion_planning_ThomX_261121.pptx
Entry   Entered by Super Team from 134.158.195.142 on Thu Nov 25 17:07:16 2021; Contrôle terminé 
Entry   Entered by Super Team from 134.158.195.142 on Thu Nov 25 16:04:39 2021; arret d'urgence 
Entry   Entered by Super Team from 134.158.195.142 on Thu Nov 25 15:54:59 2021; Test arret urgence faisceau 
Entry   Entered by Super Team from 134.158.195.142 on Thu Nov 25 15:01:41 2021; Contrôle Radioprotection 
Entry   Entered by Super Team from 134.158.195.142 on Thu Nov 25 11:19:08 2021; Mesure energie  scan_energiedeg_GUN_0.dB_LIL_2.0dB_LIL_phase_100deg_ROI__at_25-11-2021__11-14-44.jpg
Entry   Entered by Super Team from 134.158.195.142 on Thu Nov 25 11:09:21 2021; Mesure energie  scan_energiedeg_GUN_0.dB_LIL_1.5dB_LIL_phase_100deg_ROI__at_25-11-2021__11-07-51.jpg
Entry   Entered by Super Team from 134.158.195.142 on Thu Nov 25 10:52:12 2021; Transport 
Entry   Entered by Super Team from 134.158.195.142 on Thu Nov 25 10:07:10 2021; Laser 
Entry   Entered by Super Team from 134.158.195.142 on Thu Nov 25 09:24:38 2021; Démarrage 
Entry   Entered by Super Team from 134.158.195.141 on Wed Nov 24 16:52:10 2021; Mesure d'energie 
Entry   Entered by Super Team from 134.158.195.141 on Wed Nov 24 11:21:24 2021; shift du 24 Novembre 2021 charge_phase__at_24-11-2021__15-11-41.jpgScreenshot_from_2021-11-24_15-23-50.pngScreenshot_from_2021-11-24_15-51-42.png
Entry   Entered by Iryna Chaikovska from 134.158.89.93 on Tue Nov 23 13:12:22 2021; Cyclage quadrupoles Screenshot_2021-11-23_at_13.14.26.pngScreenshot_from_2021-11-23_14-09-27.pngScreenshot_from_2021-11-23_14-10-15.pngcylage_quad.pngcylage_quad2A.png
Entry   Entered by Super Team from 134.158.195.141 on Tue Nov 23 12:11:01 2021; energie laser 
Entry   Entered by Iryna Chaikovska from 134.158.195.143 on Tue Nov 23 10:56:34 2021; Cyclage dipole cylage_dipole.pngScreenshot_from_2021-11-23_12-16-04.pngScreenshot_2021-11-23_at_14.40.52.png
Entry   Entered by Super Team from 134.158.195.142 on Tue Nov 23 10:43:41 2021; run 23 nov 2021 
Entry   Entered by Super Team from 134.158.195.142 on Mon Nov 22 11:20:47 2021; run du 22 novembre 
Entry   Entered by Moutardier Alexandre from 134.158.195.144 on Fri Nov 19 09:24:11 2021; Trou dangereux !!! trou_escalier_anneau.jpg
Entry   Entered by Hayg Guler from 134.158.195.141 on Thu Nov 18 18:39:04 2021; Energies avant section pour différents gradients  