372
|
Thu Feb 24 13:37:08 2022 |
Entered by JNC/SC/CB from 134.158.195.142 on Thu Feb 24 13:36:53 2022 | | Linac | Linac Commissionning |
|
Faisceau | | Energie laser = 27 uJ sur la cathode
IHM Camera laser s'est gelé,
impossible de le rouvrir et de voir l'image |
|
|
405
|
Thu Mar 17 17:54:29 2022 |
Entered by JNC/HG/AM/SC from 134.158.195.143 on Thu Mar 17 17:54:14 2022 | Under Process | Linac | Linac Commissionning |
|
Faisceau | | MeanStd fonctionne
Cyclage des dipoles Q01 Q02 et
Q03 fait |
|
|
444
|
Thu Apr 14 16:31:58 2022 |
Entered by SC/ND from 134.158.195.141 on Thu Apr 14 16:31:44 2022 | Under Process | Linac | Linac Commissionning |
|
Faisceau | | Phase 145 degres charge max Q = 77 pC
HT = 1090 V
Energie max (-40 degres) Q = 69 |
|
|
492
|
Tue Jul 5 10:26:33 2022 |
Entered by Super Team from 134.158.195.141 on Tue Jul 5 10:26:17 2022 | Under Process | Linac | Linac Commissionning |
|
Faisceau | | 10h20 Mise en chauffe modulateur et chillers
(MO, SC)
Arret modulateur pour changement |
|
|
273
|
Thu Jan 20 18:17:56 2022 |
Entered by Super Team from 134.158.195.141 on Thu Jan 20 18:17:38 2022 | Fixed | Info | Linac Commissionning |
|
FIn de shift | | 18h20 : fin de shift
Redpitaya relancés vers
18h en redémarrant en hard |
 |
|
1203
|
Thu Mar 5 13:19:22 2026 |
MJ VM DN RC HG | | Shift summary | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
Etudes matching |
| Mesures : Spectres et taille source
X + Quads scans associées, @
|
|
|
1212
|
Sun Mar 15 18:42:53 2026 |
MJ HG VK | Fixed | Shift summary | Linac Commissionning | Ring Commissioning |
|
Etudes de points MATCHING - 13 mars 2026 | | Programme :
Etudes points Matching
============================== |
|
|
948
|
Tue Oct 29 10:31:45 2024 |
HG, SC | Under Process | Info | Linac Commissionning |
|
Etude faisceau linac | | 9h30 : Mise en chauffe
10h31 : mise en route faisceau
On se place à 0 dB, |
|
|
961
|
Thu Nov 14 09:21:51 2024 |
Entered by Viktor Soskov from 134.158.195.153 on Thu Nov 14 09:21:36 2024 | Fixed | Info | Laser |
|
Etat laser | | Bonjour, rien n'a change au faisceau
laser (distribution reste le meme,l'energie
sur la cathode =60mkJ, Iris = 1.3mm, Att |
|
|
1036
|
Thu Mar 13 11:25:29 2025 |
Entered by Viktor Soskov from 134.158.195.153 on Thu Mar 13 11:25:13 2025 | Fixed | Linac | Laser |
|
Etat laser | | Bonjour, le parcours optique a ete realigne.
L'enegie UV sur la cathode
= 48uJ , Iris = 1.3mm, Att = 410 |
|
|
1037
|
Thu Mar 13 11:57:19 2025 |
Entered by Viktor Soskov from 134.158.195.153 on Thu Mar 13 11:57:03 2025 | Fixed | Info | Laser |
|
Etat laser | | Voici les distibutions UV laser sur lacathode
avant et apres l'alignement |
 |
|
151
|
Mon Nov 8 09:21:48 2021 |
Entered by sophie chance from 134.158.195.141 on Mon Nov 8 09:21:32 2021 | Under Process | Info | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning |
|
Etat des lieux | | SC et AM
Fermeture des sous-sols et de la
crinoline |
|
|
472
|
Tue Jun 7 09:53:01 2022 |
Entered by ND/JNC/VC/VS/MO/SC from 134.158.195.141 on Tue Jun 7 09:52:47 2022 | Under Process | Linac | Linac Commissionning |
|
Etat des lieux | | Presents: SC, ND, JNC, VS, MO
Fermeture casemate
Tests des DSs en cours |
|
|
720
|
Mon Mar 27 13:55:41 2023 |
Entered by Super Team from 134.158.195.141 on Mon Mar 27 13:55:24 2023 | Under Process | Info | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
Etat ThomX | | Cavité FP a terminé son intervention
Mise sous vide possible cette après-midi
14h Intervention IHM cavité |
|
|
804
|
Tue Oct 10 13:47:16 2023 |
MJ KD | | Shift summary | Linac Commissionning | Ring Commissioning |
|
Essai de validation synchro electron / laserFPC | | ** 500.25 MHz anneau
** laser locke tres instable
** Vers 13h : IP retrouvee |
 |
|
148
|
Fri Oct 29 15:58:58 2021 |
Entered by Super Team from 134.158.195.142 on Fri Oct 29 15:58:45 2021 | Not Fixed | Linac | Linac Commissionning |
|
Erreur DS CALC sur terminal | | Message apparu dans un terminal après
avoir lancé ipython create_DS_Att_Deph_write.py
Le moteur sur l'IHM |
|
|
Draft
|
Fri Oct 29 15:56:01 2021 |
Entered by Super Team from 134.158.195.142 on Fri Oct 29 15:55:48 2021 | Under Process | Question | |
|
Erreur DS CALC | |
alexandre.moutardier@client3:~/git/panneaux/PlateformeIHMThomX$ |
|
|
171
|
Thu Nov 18 18:39:18 2021 |
Entered by Hayg Guler from 134.158.195.141 on Thu Nov 18 18:39:04 2021 | Under Process | Shift summary | Linac Commissionning |
|
Energies avant section pour différents gradients | | Methode :
on utilise le steerer LI/PS/STR01-V01
et les mesures sont faites sur le Yag de |
|
|
1208
|
Wed Mar 11 18:12:23 2026 |
Entered by Super Team from 127.0.0.1 on Wed Mar 11 18:12:09 2026 | Under Process | Shift summary | LI |
|
Emittance vs Iris | | Some Quad scans with variying the Iris
opening.
Data : |
|
|
1136
|
Mon Oct 13 13:40:05 2025 |
Hayg | Under Process | Info | Linac Commissionning |
|
Emittance QP3 | | QP3 scan
vary Soleno
Iris 1mm ATT 400 (150 pC) |
|