Draft
|
Mon Oct 3 14:08:06 2022 |
VC/KD/SC | New Solution | Linac | Linac Commissionning |
|
Faisceau linac | | 13h : MO : Mise en chauffe modulateur et
mise en route refroidissement
14h : Fermeture casemate, démarrage |
|
|
633
|
Tue Nov 29 09:18:20 2022 |
Entered by Super Team from 134.158.195.141 on Tue Nov 29 09:18:00 2022 | | Linac | Linac Commissionning |
|
Faisceau linac | | 9h15 : Mise en chauffe modulateur, mise
en route refroidissements
Clé fosse nord et fosse |
|
|
788
|
Tue Aug 1 09:21:59 2023 |
CB/JNC/SC | | Linac | Linac Commissionning |
|
Faisceau linac | | 9h20 Mise en chauffe modulateur, démarrage
frigo et laser
Permis casemate en rouge sur le |
|
|
912
|
Fri Sep 13 15:02:04 2024 |
Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 13 11:22:05 2024 | Fixed | Info | Linac Commissionning |
|
Faisceau laser UV | | Bonjour, voici l'images du faisceau
laser UV actuel sur la cathode (Iris : D=2mm,
D=6mm) |
 |
|
1073
|
Tue May 20 15:18:09 2025 |
HG, SC | Under Process | Info | LI |
|
Faisceau injecteur | | 14h : Faisceau, charge max = 200pC à
300 position attenuateur laser
15h : beaucoup de claquages dans |
 |
|
100
|
Fri Oct 8 16:11:31 2021 |
Entered by HG, SC, MO from 134.158.195.142 on Fri Oct 8 16:11:15 2021 | Fixed | Linac | Linac Commissionning |
|
Faisceau et scan charge phase | | Mise en route du faisceau.
Les paramètres RFs canon
utilisés sont attenuation : 0.75 dB, |
|
|
159
|
Tue Nov 9 11:25:33 2021 |
Entered by sophie chance from 134.158.195.141 on Tue Nov 9 11:25:18 2021 | | Info | Linac Commissionning |
|
Faisceau et scan charge phase | | Faisceau jusqu'à sortie section
reproductible depuis hier, pas de steerer
observation sur caméra sortie section |
|
|
Draft
|
Tue Oct 26 10:48:27 2021 |
Entered by CB, HG from 134.158.195.142 on Tue Oct 26 10:48:12 2021 | Fixed | Info | Linac Commissionning |
|
Faisceau et accès | | Opérateurs : CB, HG et SC
BPMs : AM et VK
Arrêt faisceau pour accès |
|
|
818
|
Thu Nov 16 08:52:14 2023 |
SC/IC/JNC/VK/HG/VM | | Anneau | LI | LE | Ring |
|
Faisceau anneau point de fonctionnement | | 8h52 : mise en chauffe modulateur et chillers,
cyclage des aimants
10h15 : Le laser n'est pas |
  |
|
723
|
Thu Mar 30 13:35:13 2023 |
Entered by SC from 134.158.195.141 on Thu Mar 30 13:34:57 2023 | Under Process | Linac | Linac Commissionning |
|
Faisceau Linac | | 14h38 : Démarrage faisceau linac
Modulateur 1090V, Position laser
horizontale 4.910 mm et verticale 2.40 mm |
|
|
725
|
Fri Mar 31 10:11:40 2023 |
Entered by Super Team from 134.158.195.141 on Fri Mar 31 10:11:25 2023 | | Linac | Linac Commissionning |
|
Faisceau Linac | | 10h12 Démarrage modulateur et refroidissement
Lancement de l'archivage
11h05 Fermeture casemate |
|
|
726
|
Fri Mar 31 10:44:31 2023 |
Entered by Super Team from 134.158.195.141 on Fri Mar 31 10:11:25 2023 | | Linac | Linac Commissionning |
|
Faisceau Linac | | Qui me pique internet ?
Et m'éfface le elog
? |
|
|
729
|
Thu Apr 6 12:57:29 2023 |
Entered by Super Team from 134.158.195.141 on Thu Apr 6 12:57:15 2023 | | Linac | Linac Commissionning |
|
Faisceau Linac | | 12h57 Mise en chauffe modulateur et refroiddissement
canon et section
Vide dans l'anneau de l'ordre |
|
|
730
|
Fri Apr 7 13:48:55 2023 |
Entered by Super Team from 134.158.195.141 on Fri Apr 7 13:42:08 2023 | | Linac | Linac Commissionning |
|
Faisceau Linac | | Programme :
- Mesure Energie apres section
en fonction de la phase avec steerer sur |
|
|
731
|
Tue Apr 11 12:59:18 2023 |
Entered by Super Team from 134.158.195.141 on Tue Apr 11 12:59:03 2023 | | Linac | Linac Commissionning |
|
Faisceau Linac | | 13h : Mise en chauffe modulateur et refroidissement
14h34 Faisceau, HT = 1090V, HoPoslaser
= 5.039, vertposlaser = 2.291, attenuation |
|
|
Draft
|
Fri Apr 21 14:30:19 2023 |
Entered by Super Team from 134.158.195.141 on Fri Apr 21 14:30:03 2023 | | Linac | Linac Commissionning |
|
Faisceau Linac | | 13h49 Démarrage faisceau
Position laser H = 4.9 et V = 2.42,
scan charge phase : phase de focalisation |
|
|
681
|
Thu Feb 16 11:31:36 2023 |
MJ, HG | Under Process | Shift summary | Linac Commissionning |
|
Faisceau LI/TL | |
Phase Qmax : 300 degres
-->
Phase Emax = 250
|
  |
|
822
|
Thu Nov 23 08:51:44 2023 |
SC/KD | | Anneau | LI | TL | LE | Ring |
|
Faisceau LE | | 8h50 Mise en chauffe modulateur
Mise en route chillers et frigo
Problème laser photocathode |
|
|
578
|
Thu Oct 6 10:18:03 2022 |
VK/ND/SC | | Anneau | Ring Commissioning |
|
Faisceau Anneau | | Modulateur Impossible à passer en
Standby ==> problème manque d'eau.
|
10x |
|
141
|
Thu Oct 28 17:36:27 2021 |
Entered by sophie chance from 134.158.195.141 on Thu Oct 28 17:36:11 2021 | Fixed | Linac | Linac Commissionning |
|
Faisceau 10 Hz | | Bobine de foc I = 170A, 10 Hz, image sortie
canon jointe
Estimation de la charge : Q = 50 |
|