Entry   LS, ND; shift du 29 juin 2023 

9:45 Git pull

Test des interfaces... OK

Probleme sur les ecrans du compte operateur ThomX (4x1 ecran) meme apres redemarrage => reconfiguration

10:10 Mise en chauffe

Interlock sur les aimants vu pendant le cyclage. Resolu.

11:30 Faisceau

12:05 Allumage cavite anneau (MEK)

12:15 Perte faisceau...

Apparement le PA avait disjoncte. Intervention MO.

13:00 Retour faisceau

Prise de données TL/FC01

13:30 Transport dans EL, essaie d'amélioration du transport : on a réussi à transporter environ 1/3 de la charge 

Prise de données dans EL/FC01 

15:00 Stockage dans anneau, optimisation 

16:00 Prise de données pour étudier les pertes dans les fibres. 

Prise de données des pertes:

-sans faisceau, avec juste kicker d'injection, septum, ou kicker d'extraction

-sans faisceau, avec tous les EP : obtenir bruit de fond

-avec faisceau, avec juste kicker d'injection, septum, ou kicker d'extraction 

-avec faisceau: prise de données avec différents timing pour le kicker d'extraction => extraire le faisceau pour comprendre le timing de l'acquisition et observer les pertes avec différents timing de d'extraction

Entry   ND, Anna K, Elene K, Marie L; Prise de donneees 5/02 mrsv_nobeam.pngmrsv_beam.png

Coordinator: ND

9h12: Modulator start

PSS: Default centrale SSI

10h30 Beam

Load recipe: LI_TL_straight_test_20231027_11_21_15

12:15 Lunch break

Strange message left on one of the computer screens.

14:15: The shutter was moved over lunch time without it being logged.

14h20 Access to check MRSV

14h40 Restart beam

Some signal observed beam on and not beam off. But strongly misaligned.

Several access, trying to align the MRSV. No luck. More time to be spent on it.

17h30 Stop beam

 

Entry   Entered by Super Team from 134.158.195.141 on Fri Jun 7 09:24:42 2024; Interventions du matin 

9h Intervention sur les filtres de la CTA (Dalkia, Stéphane)

9h Intervention dans les sous-sols (infra) pour le pompage, ouverture des grands vantaux

9h20 CTA remise en route accès à la casemate à nouveau possible

9h20 Intervention Dalkia concernant les réglages de la pompe, arrêt de la pompe à prévoir qui va durer au moins toute la matinée

Cable coupé controlé par le SPR : ok pas de soucis, cable posé sur les dosimètres

L'intervention sur les pompes de la fosse nord n'est pas terminé et continuera cette apres midi : besoin acces fosse nord

 

 

Entry   KD; mesure laser PC du 20 aout 2024 2024-08-20_16_10_28_li_op_las_02_RAW.png2024-08-20_16_11_18_li_op_las_02_RAW.png2024-08-20_16_11_31_li_op_las_02_RAW.png

Mesure du Laser Photocathode le 20 aout 2024:

prise de la forme du faisceau sur la PhotoCathode Virtuelle pour différente taille d'iris : 7mm (ouverture max), 3mm, 1.3mm

Prise de puissance laser atténuateur à 410 pas :

sortie Laser : 295 uJ

Sortie Iris :

1.3mm : 70uJ

7mm (ouverture max) : 202 uJ

Entree canon :

iris 1.3mm : 53 uJ

iris 7mm (ouverture max) : 135 uJ

 

l'Iris a ete reconfigurée (bug dans le retour de position).

 

Entry   KD; laser PC  2024-11-22_11_07_23_li_op_las_02_RAW.png2024-11-22_11_07_57_li_op_las_02_RAW.png

Mesure de ce matin et réalignement:

sortie laser : 298uJ

sortie ligne de transport : 209uJ

sortie iris 1.3mm: 80uJ

Injection canon: 60uJ@420pas

voir image faisceau

Entry   KD; alignement laser PhotoCathode 

Mesure de ce matin et changement point cathode [H,V] = [4.29,3.49]:

sortie laser : 275 - 280uJ

sortie ligne de transport : 184uJ

sortie iris 1.3mm: 73uJ

Injection canon (iris 1.3mm): 56uJ@420pas

Injection canon (iris 1.3mm): 45uJ@350pas

icon4.gif   VS, AG, KD; changement PhotoCathode 6x

lundi 5 mai : remise à l'air et démontage de l'ancienne cathode (Cu)

- Le faiscea laser est remis sur les réferences et le faisceau passe au travers de la cathode trouée (OK pour le Mg). NB. Le trou de la cathode trouée fait la taille de la pastille de Mg. (cf. Photos)

- démontage et inspection du hublot et miroir de renvoie sous vide (démontage de l'ICT pour accéder au miroir de renvoie) :

      * le Hublot semble ok mais il est salle sur la face à l'air ==> nettoyage

      * le miroir de renvoie est piqué (impacts laser) de plus il est éclaté (casse du substrat sûrment dû à des arcages) ==> changement du miroir

          ** Impossibilité de le mettre sans réhausse en fasse arrière (clinquants).

          ** Les griffes de maintien sont mises plus fortement en appuis sur le miroir. 

          ** Contact électrique vérifié entre la face avant (dépôt argent) et le support.

 

 

mardi 6 : alignement laser sur la cathode trouée

- le faisceau est réaligné au centre de la cathode trouée. Nouvelle position de référence sur la caméra PhotoCathode [H,V] =  [5.55, 3.35]

- mesure de puissance laser Photocathode :

sortie Iris :

@1.3mm 20uJ

@3mm 57uJ

@7mm 93uJ

injection canon atténuateur @420pas :

@1.3mm 18uJ

@3mm 48uJ

@7mm 78uJ

sortie canon (sur la cathode Mg) atténuateur @420pas :

@1.3mm 14uJ

@3mm 40uJ

@7mm 63uJ

 

mercredi 7 mai : remise sous vide du canon (~12h), cathode installée depuis 16h la veille

- mesure/calibration atténuateur pour limiter l'énergie laser à 5-10uJ (pour débuter)

icon7.gif   Entered by Aurélien Martens from 134.158.88.183 on Tue May 28 15:07:25 2019; Photocathode laser DS back operational 

Following:

1) a crash on 4th of April and a violent reboot of the ELLiOOs embeded machine

2) the need to recover the whole database files in the ELLiOOs embeded machine

the ElliOOs sofware was running back quickly. Though recently (in terms of working and available days) was reported that the tango DS was not communicating.

The reason why stayed misterious.

Following calls to Amplitude Laser (Vianney) last week and, today, a callabck from SCARELL (Romain and Jean-François), it is now understood that :

- the content of the data repository corresponding to the Tango gateway was not dynamically created (~/bin/ElliOOs/User/Data/28*/*). The specific file that was missing since the 5th of arpil reeboot was Plugin.sml.

Recovering this file and properly rebooting the embedded machine (from the ElliOOs programme running on the HOST, in the System Info --> reboot embedded), allowed to revoer the com.

Indeed it was checked by looking at jive by Falcoz.

An archive of the Code repository was done in case it is required to recover these files again. Archive sent to SCARELL.

Please remember to reboot the embeded in case there is a reoboot of TANGO machine in the main control room or if the database is reset.

Please also note that trying to look at the content of the TANGO_HOST variable in superuser or default user will not help in understanding if tango is running locally.

 

Entry   Entered by talour from 134.158.205.2 on Thu Apr 8 21:11:41 2021;  
 
Entry   Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 10:40:40 2021; Fermeture sous-sols et toit casemate 

Les sous-sols et le toit sont maintenant fermés

Entry   Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 14:48:07 2021;  

LI/HFI/ATT.02-MOT.01 Attenuateur Canon

Entry   Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 14:49:35 2021; attenuateur section tests butée moteur 

ATT01-MOT01 atténuateur section course de -870 step à 2485 pour les butées

Entry   Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 15:05:59 2021;  

ATT02-MOT01 attenuateur canon en butée à -8 jusque 3329

Entry   Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 17:04:28 2021; Hv sur modulateur 

Sur le MPS, Vérifiez qu'on est bien en PARAMETRES/ Linac pour autorisation HV sur modulateur

Entry   Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 17:15:58 2021;  

Modulateur OK, HT = 500 V en trig

Entry   Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 17:29:26 2021;  HT_1100.png

Capture ecran modulateur

Entry   Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 17:40:07 2021; Résumé de la journée 

- Pour les atténuateurs : les butées ont été trouvées, ATT02-MOT01 c'est la canon, ATT01-MOT01 c'est la section.

- Des difficultés ont été rencontrés avec le modulateur : Interlock à cause de l'eau, interlock alim HT, reboot modulateur et vérification de l'autorisation de tir MPS faite.

Le modulateur fonctionne maintenant sans problèmes à une tension de 1240V et un vide klystron de 1.2 uA qui devrait diminuer par la suite. Les mesures radioprotection ont été faites

- Pour le MPS, cliquez sur Paramètres en bas de l'écran principal puis vérifier que LINAC est on.

Pour demain :

- Démarrer régulation eau en plus du modulateur

- Vérifier les signaux RFs sur oscillo et Réglage des retards (demarrage_delays)

- Ne pas mettre beaucoup de puissance, vérifier la chaine RF et vérifier les atténuateurs

- Vérifier caméra et ICT

Entry   Entered by bruni from 134.158.195.141 on Wed Jun 9 18:11:49 2021; Mise en route RF +PA tension_puissance_klystron_canon_section.ods

HT on, on met le PA

On met la HT à 500V, soit 128 kV de HT klystron. On mesure avec le crystal numero 8. On doit avoir selon la règle de calibration avec une atténuation de 70 dB, 0.349 MW

On change la largeur HF de 2 à 1 us, la HT est tombée. Faire des tests de corrélation timing/klystron

Défaut d'eau sur le modulateur. Suite de l'ouverture d'une vanne pour les tests de cavité RF anneau.

On remet le modulateur en chauffe. On met une durée de 2 us, avec 500V--> 650V, on voit un petit signal Pic

A 730V de HT, on mesure 0.3mV, qui nous fait 0.3kW, or la mesure klystron nous indique 0.8MW. On devrait donc avoir 1/3 au canon. On vérifie que l'atténuateur sur guide est bien au minimum.

On a des claquages sur le PIK.

On voudrait changer un des réglages de la synchro. L'IHM ne répond pas --> Hayg regarde

    2 incident klystron 334 70 0 0 1.00E-07 8 6.88E-08 6.13E-04 9.93E-02 1 50 1.041
      incident canon 0.25 70 0 0 1.00E-07 1 1.11E-07 9.80E-04 1.07E-01 0.98 50 0.0003
730   2 incident klystron 8.226 70 19.9 0 1.02E-09 8 6.88E-08 6.13E-04 9.93E-02 1 50 0.839
      incident canon 0.385 70 0 0 1.00E-07 1 1.11E-07 9.80E-04 1.07E-01 0.98 50 0.0004
730   2 incident klystron 8.226 70 19.9 0 1.02E-09 8 6.88E-08 6.13E-04 9.93E-02 1 50 0.839
      incident canon 0.3 70 0 0 1.00E-07 1 1.11E-07 9.80E-04 1.07E-01 0.98 50 0.0003

Tout est à zero, on charge la recette synchro de mars 2021.

On n'arrive pas à piloter les retards, on n'a pas le temps de taper dans l'IHM.

On arrête.

 

     
Entry   Entered by bruni from 134.158.195.141 on Wed Jun 9 21:48:07 2021; reporting du 9 juin, et planning du 10 juin matin 

Nous avons procéder au debuguage de la RF, principalement des réglages de synchro delai et IHM.

On dispose à présent du PIk en salle de controle sur l'oscilloscope

les atténuateurs ont été réglés pour le canon et la section

Un fichier excell a été préparé pour obtenir les puissance incidente et réflechie à partir des chaines, ranger dans commissiong tools

On a pu voir le signal Pic du canon. les puissances ne correspondent pas à ce qu'on attend

Pour demain matin : régler le problème de l'IHM delay qui nous empeche de saisir un chiffre

Rerégler les retards du PA et faire une nouvelle recette. Vérifier les chaines de mesure car les puissance ne correspondent pas.

Vérifier l'absnce de claquage en amont du circulateur à 0.5us de largeur RF

 

Entry   Entered by bruni from 134.158.195.141 on Thu Jun 10 13:59:50 2021; Réglage des retards reglage_des_retards_100621.png
 