HOME Prise de donnees MML Controle commande Simulations Notes Hardware Ligne X Laser Interaction Diagnostiques Synchronisation
Commissionning Commissionning Preparation Pannes ShiftCheck
  Toutes les notes concernant les Commissionning de ThomX, Page 17 of 58  Not logged in ThomX    logo
New entries since:Thu Jan 1 01:00:00 1970
Entry   SC, HG, MJ; Alignements : LASER - SOLENO - SECTION 2024-09-10-alignement-section.pdfprochain_alignement_section.xlsx
Entry   Entered by Vincent Chaumat from 134.158.76.115 on Tue Sep 10 08:29:15 2024; Cablage Repitaya Baie 17 
Entry   KD-VM-VC; shift du 4 septembre 2024 TL_SST2_Screenshot_from_2024-09-04_17-27-45.png2024-09-04_17_29_44_tl_dg_sst_01-ccd_01_RAW.png2024-09-04_17_32_29_li_dg_sst_01-ccd_01_RAW.png
Entry   SC, KD, HG MJ; Alignement laser et section + Mesures cathod_align_dark_current.png
Entry   Entered by Vincent Chaumat from 134.158.76.115 on Fri Aug 30 15:15:02 2024; Synchro 
Entry   KD; mesure laser PC du 20 aout 2024 2024-08-20_16_10_28_li_op_las_02_RAW.png2024-08-20_16_11_18_li_op_las_02_RAW.png2024-08-20_16_11_31_li_op_las_02_RAW.png
Entry   KD MJ VK; shift du 21 aout 2024 2024-08-21_16_09_39_li_dg_sst_01-ccd_01_RAW.pngTl_sst1_Screenshot_from_2024-08-21_16-18-45.png2024-08-21_16_57_54_tl_dg_sst_02-ccd_01_RAW.pngcalibration_SST_20240821.pptx
Entry   M ELK; validation de conditionnement 16/08 RF_signalsScreenshot_Redpitaya_0.1dB_3µs_25Hz__2024-08-16.pngRF_signalsScreenshot_scope_0.1dB_3µs_25Hz__2024-08-16.png
Entry   M ELK; Suite conditionnement section 13/08 pour validation  Scope_RF_signals_0.1dB_3µs_25Hz_13082024.pngRedpitaya_RFsignals_0.1_dB_3µs_25_Hz_13082024.png
Entry   Entered by Super Team from 134.158.195.142 on Fri Aug 9 10:01:08 2024; conditionnement section 
Entry   Entered by Super Team from 134.158.195.142 on Thu Aug 8 10:12:02 2024; conditionnement section 
Entry   Entered by Super Team from 134.158.195.142 on Tue Aug 6 09:57:28 2024; Commissioning section accélératrice 
Entry   Entered by Super Team from 134.158.195.141 on Mon Aug 5 10:49:42 2024; Suite conditionnement section 
Entry   VM, HG, RC, SC; RF conditionning : 2 aout  
Entry   Iryna, Sophie, Viktor, Slava; conditionnement de la section RF@ 3µs & 25 Hz  14x
Entry   M.O, M ELK, Slava , Iryna; Conditionnement section 31/07 image_de_splitter_.pngbreakdown_25Hz_3us_09dB_14h52.png
Entry   M.O, M ELK, Hayg, Slava; Conditionnement section SC/ME/MO/VK/HG  Vide_Screenshot_2024-07-30_17-13-24.png
Entry   M ELK, Slava, Iryna, Hayg; Conditionnement section 29/07 Interlock_Sec_0.2dB_10Hz_3µs_15_19.pngInterlock_Sec_0.2dB_10Hz_3µs_15_35.png
Entry   M.O, M ELK , Iryna, Hayg; Conditionnement section 26/07 0.1dB_2us_10Hz_16-41-51.png0.1dB_2us_10Hz_16-34-07.pn0.1dB_2us_10Hz_17-15.png
Entry   M ELK, SC, MO ; Conditionnement section 25/07 0.7_dB_3µs_10Hz__13h04__claquage_réseau_HF.png0.3dB_3us_10Hz_16h35.png1dB_3us_10Hz_16h38.png
ELOG V3.1.4-395e101