HOME Prise de donnees MML Controle commande Simulations Notes Hardware Ligne X Laser Interaction Diagnostiques Synchronisation
Commissionning Commissionning Preparation Pannes ShiftCheck
  Toutes les notes concernant les Commissionning de ThomX, Page 16 of 58  Not logged in ThomX    logo
Entry   MJ; Diags completement instables SUBITEMENT il y a 10 minutes.  
Entry   KD MJ; shift du 19 septembre 2024 
Entry   KD MJ HG; Shift du 17 septembre 2024 9x
Entry   Entered by Marie Jacquet from 134.158.205.56 on Mon Sep 16 23:59:00 2024; alignement section de lundi 16/09 
Entry   VC; Shift summary 
Entry   Entered by Super Team from 134.158.195.141 on Fri Sep 13 17:05:25 2024; Shift du Vendredi (soir) 
Entry   Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 13 11:22:05 2024; Faisceau laser UV  IrisD2mm_Image2024-09-13_10-15-56.pngIrisD6mm_Image2024-09-13_11-13-57.png
Entry   Entered by Marie Jacquet from 134.158.89.45 on Wed Sep 11 12:30:36 2024; tableau alignement section - v2 2024-09-11_alignement_section-v2_1.xlsx
Entry   VC KD; Commisionning linac set 2024 
Entry   SC, HG, MJ; Alignements : LASER - SOLENO - SECTION 2024-09-10-alignement-section.pdfprochain_alignement_section.xlsx
Entry   Entered by Vincent Chaumat from 134.158.76.115 on Tue Sep 10 08:29:15 2024; Cablage Repitaya Baie 17 
Entry   KD-VM-VC; shift du 4 septembre 2024 TL_SST2_Screenshot_from_2024-09-04_17-27-45.png2024-09-04_17_29_44_tl_dg_sst_01-ccd_01_RAW.png2024-09-04_17_32_29_li_dg_sst_01-ccd_01_RAW.png
Entry   SC, KD, HG MJ; Alignement laser et section + Mesures cathod_align_dark_current.png
Entry   Entered by Vincent Chaumat from 134.158.76.115 on Fri Aug 30 15:15:02 2024; Synchro 
Entry   KD; mesure laser PC du 20 aout 2024 2024-08-20_16_10_28_li_op_las_02_RAW.png2024-08-20_16_11_18_li_op_las_02_RAW.png2024-08-20_16_11_31_li_op_las_02_RAW.png
Entry   KD MJ VK; shift du 21 aout 2024 2024-08-21_16_09_39_li_dg_sst_01-ccd_01_RAW.pngTl_sst1_Screenshot_from_2024-08-21_16-18-45.png2024-08-21_16_57_54_tl_dg_sst_02-ccd_01_RAW.pngcalibration_SST_20240821.pptx
Entry   M ELK; validation de conditionnement 16/08 RF_signalsScreenshot_Redpitaya_0.1dB_3µs_25Hz__2024-08-16.pngRF_signalsScreenshot_scope_0.1dB_3µs_25Hz__2024-08-16.png
Entry   M ELK; Suite conditionnement section 13/08 pour validation  Scope_RF_signals_0.1dB_3µs_25Hz_13082024.pngRedpitaya_RFsignals_0.1_dB_3µs_25_Hz_13082024.png
Entry   Entered by Super Team from 134.158.195.142 on Fri Aug 9 10:01:08 2024; conditionnement section 
Entry   Entered by Super Team from 134.158.195.142 on Thu Aug 8 10:12:02 2024; conditionnement section 
ELOG V3.1.4-395e101