Message ID: 975     Entry time: Fri Dec 6 08:24:36 2024
 Author: VM, IC, VK, HG  
 Status: Under Process 
 Type: Shift summary 
 Category: Ring Commissioning 
 Important:
 Subject:  
 Icon:  

08h25 Start ThomX

09h55 HV is 'ON'

10h18 RF Gun Phase is 159 dg. Sect. Phase is 208 dg. Att. 2.66 TL/BPM2 X=-2mm, Isol =230 A, Charges: -115 pC, -95.7 pC, -100 pC

Beam injected to the Ring. There is storage there.

10h25 Ring RF is 'On', 100 kV. Storage OK

10h35 Extraction kicker is 'ON' del. is -12.4 us

10h37 TL/BPMé X=+1 mm to minimize synchrotron oscillations. Tune is 0.17

Response matrix measuring

11h45 70 MeV Receipt for 70 MeV with storage: Sect. Att is 0.204, Phase Sect is 237 dg.

12h00 RF 50 kV Beam is killed by RF

12h10 Change frequency to 500.08095 MHz

Many scans in Frequency- slow no result. Tune optics.

17h30 Hayg by scanning RF found correct frequency : 500.0325 . Recipie : Hayg 70.

Good storage!

 

 

 

 

 

 

 

 

 

Attachment 1: Screenshot_from_2024-12-06_18-30-01.png  65 kB  Uploaded Fri Dec 6 18:35:47 2024  | Hide | Hide all | Show all
Screenshot_from_2024-12-06_18-30-01.png
Attachment 2: Screenshot_from_2024-12-06_17-52-04.png  49 kB  Uploaded Fri Dec 6 18:35:47 2024  | Show | Hide all | Show all
Attachment 3: Screenshot_from_2024-12-06_16-06-03.png  117 kB  Uploaded Fri Dec 6 18:35:47 2024  | Hide | Hide all | Show all
Screenshot_from_2024-12-06_16-06-03.png
Attachment 4: Screenshot_from_2024-12-06_13-23-32.png  126 kB  Uploaded Fri Dec 6 18:35:47 2024  | Hide | Hide all | Show all
Screenshot_from_2024-12-06_13-23-32.png
Attachment 5: Screenshot_from_2024-12-06_13-22-00.png  93 kB  Uploaded Fri Dec 6 18:35:47 2024  | Hide | Hide all | Show all
Screenshot_from_2024-12-06_13-22-00.png
Attachment 6: Screenshot_from_2024-12-06_11-58-51.png  232 kB  Uploaded Fri Dec 6 18:35:47 2024  | Show | Hide all | Show all
Attachment 7: Screenshot_from_2024-12-06_11-57-22.png  206 kB  Uploaded Fri Dec 6 18:35:47 2024  | Hide | Hide all | Show all
Screenshot_from_2024-12-06_11-57-22.png
Attachment 8: Screenshot_from_2024-12-06_11-44-27.png  369 kB  Uploaded Fri Dec 6 18:35:47 2024  | Hide | Hide all | Show all
Screenshot_from_2024-12-06_11-44-27.png
ELOG V3.1.4-395e101