Message ID: 963     Entry time: Fri Nov 15 12:13:42 2024
 Author: Entered by Nicolas Delerue from 134.158.195.144 on Fri Nov 15 12:13:26 2024 
 Status: Not Fixed 
 Type: Info 
 Category: TL 
 Important:
 Subject: Charge excess in the TL 
 Icon:  

By looking at the BPM transmission tool one can see that there is more charge on TL/BP.03 than on TL/BPM.02 (see attached image).

The BPM seetings have been checked and they are similar.

One can see a similar effect when comparing TL/ICT.01 and TL/ICT.02.

Possible interpretation: the beam is scrapping the beam pipe and creating a shower of secondaries.

Attachment 1: Screenshot_from_2024-11-15_12-12-55.png  37 kB  | Show | Show all
Attachment 2: Screenshot_from_2024-11-15_12-12-46.png  78 kB  | Show | Show all