Message ID: 866     Entry time: Thu May 23 08:19:19 2024
 Author: M EK, ND, Iryna, Victor 
 Status: Under Process 
 Type: Linac 
 Category: LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning 
 Important:
 Subject: Conditionnement section 23/05 
 Icon:  

8h15: set to standby Modulateur

démarrage frigo et chiller section

la veille difficile de franchir 0.7 dB (Pis= 22 MW ) @2µs & 1Hz

retour à 1µs & 1Hz descente jusquà 0.2 dB correspondant à 25 MW ( pour éviter le bloquage du moteur de l'atténuateur)

démarrage cond. 2 dB @ 2µs & 1 Hz et redescente progressive de l'atténuation

interlock reflechi Klystron sachant au niveau de la section les puissances RF sont correctes

mise de l'atténuateur section à 12 dB et vérifier si interlock Klystron persite ==> confirmation de coupure HF ( renvoi Trig Off) à plusieurs niveaux d'alimentation de 1220 V jusqu'à 1000 V

intervention de Maher pour identifier le problème ==> pb software . Maher mise en marche en local ok et puis repassage en mode remote c'est ok à nouveau

12:56 Pause repas

13:30 resstart

We work @ 2µs & 1 Hz  Goal: to go from 3 dB to 0.2 dB

Several interlocks at 1.5dB, 0.9dB, 0.6dB. Going up to 1.5 dB and then again to 0.6 dB

Breakdowns were originated probably in the RF network. Only few in the RF section.

Setting up the wawecatcher to monitor the charge with the ICT after the RF structure. During the shift, no signal was observed.

@0.6dB several breakdowns. Coming back to 1dB, still there are breakdowns. Set 1.5dB, then 2dB.

Reached 0.6dB for short time.

17:35 We stop at 1 dB. To be continued tomorrow.

Attachment 1: RF_signals_1.7dB_1µs_1Hz  864 kB  Uploaded Thu May 23 15:20:26 2024
Attachment 2: Att1dB_2us_1Hz_2024-05-23_14-51-45.png  291 kB  Uploaded Thu May 23 18:02:08 2024  | Show | Show all
Attachment 3: Scr_0.6_us_0.6_dB_2024-05-23_17-01-31.png  264 kB  Uploaded Thu May 23 18:02:31 2024  | Show | Show all