Message ID: 856     Entry time: Thu Mar 7 08:58:28 2024
 Author: VK, VM, IC 
 Status: Under Process 
 Type: Shift summary 
 Category: Ring Commissioning 
 Important:
 Subject: Recomissioning of the SR, search for the X-rays 
 Icon:  

8h50 Warming up the machine

Problem with the vaccum around the RF cavity (see screenshot attached). Intervention of vacuum team is needed.

Mohamed is installing the powermeter to monitor the incomingt RF power for the accelerating structure.

Laser camera should be checked before the beam start-up

Due to the vaccum cable connector we can not start the beam.

Attachment 1: Screenshot_from_2024-03-07_09-02-36.png  75 kB  | Show | Show all