Message ID: 780     Entry time: Fri Jun 30 13:14:30 2023
 Author: LS,ND 
 Status: Under Process 
 Type: Shift summary 
 Category: Ring 
 Important:
 Subject: run du 30 juin 2023 
 Icon:  

9:00 Warm up machine

10:40 Start the beam

10:50 Scan charge phase 

11:15 Storage in  ring

Recipe: recipe_recipe_LI_TL_RI_test_20230629_16_44_31.txt

11:30 Studies of losses with fiber inside ring 

12:30 Start RF cavity

13:00 Scan phase cavity

 

 

 

 

Attachment 1: health_check_2023_06_30_13_20.png  18 kB  Uploaded Fri Jun 30 14:22:35 2023  | Hide | Hide all | Show all
health_check_2023_06_30_13_20.png
Attachment 2: scan_charge_phase_min_280.0_max_320.0_10_54_10.png  42 kB  Uploaded Fri Jun 30 14:23:04 2023  | Show | Hide all | Show all