Message ID: 695     Entry time: Thu Feb 23 10:08:35 2023
 Author: ND, VK, VM 
 Status: Under Process 
 Type: Shift summary 
 Category: Ring Commissioning 
 Important:
 Subject: Shift 23/2 
 Icon:  

9h22 mise en chauffe

 

Pb site elog; autres sites web OK

 

Health check OK

 

10:00 Cyclage aimants 0K

 

10:59 Demarrage

 

12:00 Emittance scan

 

Transport beam through TL. Attenuator 1.6dB. Check that beam is similar in simulation and on the screens.

 

Beam image at each screen station for current transport (images to attach).

 

 

Transport till ring with nominal TL optics. All charge is transported.

 

Check dispersion to be nonzero for later compensation in dpi and septum.

 

TL QP5 changed to from 2.2 to 1.5. Impoved injection stability, this value is far from; the theoretical one. to be studied.

 

Optimisation of injection with RCDS.

 

Undure curernt conditions beam SPX = 2 and SpY = 1 @ ric1 / BPM.02 stable.

 

Libera 4 freezed. Restart did not helped to recover BPM05-Lib04; Others after restart working well. Sever restart with astor solved the problem.

 

 

Saved data to reconstruct orbit

 

 

17:00 Arrêt machine

 

Attachment 1: health_check_2023_02_23_09_27.png  15 kB  | Hide | Hide all | Show all
health_check_2023_02_23_09_27.png
Attachment 2: scan_charge_phase_min_0.0_max_360.0_11_9_18.png  48 kB  Uploaded Thu Feb 23 11:10:21 2023  | Hide | Hide all | Show all
scan_charge_phase_min_0.0_max_360.0_11_9_18.png
Attachment 3: scan_charge_phase_min_260.0_max_300.0_11_10_2.png  43 kB  Uploaded Thu Feb 23 11:10:32 2023  | Hide | Hide all | Show all
scan_charge_phase_min_260.0_max_300.0_11_10_2.png
Attachment 4: Screenshot_from_2023-02-23_17-16-26.png  64 kB  Uploaded Thu Feb 23 17:18:52 2023  | Hide | Hide all | Show all
Screenshot_from_2023-02-23_17-16-26.png
Attachment 5: Screenshot_from_2023-02-23_17-16-16.png  64 kB  Uploaded Thu Feb 23 17:19:00 2023  | Hide | Hide all | Show all
Screenshot_from_2023-02-23_17-16-16.png
Attachment 6: ring_vars_2023_02_23_17_14.png  28 kB  Uploaded Thu Feb 23 17:19:06 2023  | Hide | Hide all | Show all
ring_vars_2023_02_23_17_14.png
Attachment 7: Screenshot_from_2023-02-23_17-06-26.png  122 kB  Uploaded Thu Feb 23 17:19:15 2023  | Show | Hide all | Show all
Attachment 8: Screenshot_from_2023-02-23_16-31-06.png  67 kB  Uploaded Thu Feb 23 17:19:26 2023  | Show | Hide all | Show all
Attachment 9: Screenshot_2023-02-24_at_14.26.46.png  303 kB  Uploaded Fri Feb 24 14:32:12 2023  | Show | Hide all | Show all