HOME Prise de donnees MML Controle commande Simulations Notes Hardware Ligne X Laser Interaction Diagnostiques Synchronisation
Commissionning Commissionning Preparation Pannes ShiftCheck
  Toutes les notes concernant les Commissionning de ThomX  Not logged in ThomX    logo
Message ID: 649     Entry time: Fri Dec 9 11:07:57 2022
 Author: Entered by Super Team from 134.158.195.141 on Fri Dec 9 11:07:40 2022 
 Status: Under Process 
 Type: Anneau 
 Category: Ring 
 Important:
 Subject:  
 Icon:  

Phase Qmax = 138

Phase Emax = 88

energy jitter

RF Cavity interlock vacuum - reset with DS .

Search optimal phase of RF cavity.

 

16:50 Closing the scrapper: less losses at injection

Best scrapper setting L=35mm R=9mm

17:30 Demarrage Kicker extraction

Pelser3fault and Pulser4fault on Extraction Kicker => Impossibele to start

 

 

 

 

Attachment 1: Screenshot_from_2022-12-09_16-53-05.png  824 kB  Uploaded Fri Dec 9 16:53:22 2022  | Hide | Hide all
Screenshot_from_2022-12-09_16-53-05.png
Attachment 2: Screenshot_from_2022-12-09_16-52-44.png  60 kB  Uploaded Fri Dec 9 16:53:31 2022  | Hide | Hide all
Screenshot_from_2022-12-09_16-52-44.png