Message ID: 647     Entry time: Thu Dec 8 10:05:38 2022
 Author: ND, IC, VK, VM, ME 
 Status: Under Process 
 Type: Shift summary 
 Category: Ring | Ring Commissioning 
 Important:
 Subject: Shift 8/12 
 Icon:  

9h: Mise en Chauffe modulateur + Frigo + Laser
Il n'y a plus de perte de pression ce matin. La fuite du Solénoide semble avoir été la cause.

10:05 Acces SPR en fosse pour installation dosimetre Radon

Phase Max foc : 133
Phase Emax : 83 environ (sachant que Phase Max foc ~ Phase Q max +/- 2 degrés)
Ekin (@83°) = 4.83 MeV

12:00 Trying new frequency for the ring

More than a 1000 turns

13:20 Storage!!!!!

f=500.415MHz

 

 

Fine search for reduce orbit.

Tuned Cavity to Freq.

Cavity voltage 34.48 kV

Freq = 500.4138

Bam storage more than 100000 Turns. Milestone achieved !

Data taking

Cavity voltage 75.0 kV

Cavity voltage 123.0 kV

 

 

Attachment 1: Screenshot_from_2022-12-08_12-02-39.png  72 kB  Uploaded Thu Dec 8 12:04:22 2022  | Hide | Hide all | Show all
Screenshot_from_2022-12-08_12-02-39.png
Attachment 2: Screenshot_from_2022-12-08_12-05-24.png  783 kB  Uploaded Thu Dec 8 12:05:36 2022  | Hide | Hide all | Show all
Screenshot_from_2022-12-08_12-05-24.png
Attachment 3: scan_charge_phase_min_0.0_max_360.0_12_16_56.png  48 kB  Uploaded Thu Dec 8 12:17:26 2022  | Hide | Hide all | Show all
scan_charge_phase_min_0.0_max_360.0_12_16_56.png
Attachment 4: scan_charge_phase_min_80.0_max_160.0_12_18_20.png  52 kB  Uploaded Thu Dec 8 12:18:37 2022  | Hide | Hide all | Show all
scan_charge_phase_min_80.0_max_160.0_12_18_20.png
Attachment 5: Screenshot_from_2022-12-08_12-47-00.png  74 kB  Uploaded Thu Dec 8 12:47:15 2022  | Show | Hide all | Show all
Attachment 6: Screenshot_from_2022-12-08_12-48-35.png  74 kB  Uploaded Thu Dec 8 12:48:45 2022  | Show | Hide all | Show all
Attachment 7: Screenshot_from_2022-12-08_13-01-08.png  68 kB  Uploaded Thu Dec 8 13:01:23 2022  | Hide | Hide all | Show all
Screenshot_from_2022-12-08_13-01-08.png
Attachment 8: Screenshot_from_2022-12-08_13-07-56.png  71 kB  Uploaded Thu Dec 8 13:08:10 2022  | Show | Hide all | Show all
Attachment 9: Screenshot_from_2022-12-08_13-16-30.png  70 kB  Uploaded Thu Dec 8 13:16:52 2022  | Show | Hide all | Show all
Attachment 10: Screenshot_from_2022-12-08_13-28-55.png  818 kB  Uploaded Thu Dec 8 13:29:09 2022  | Hide | Hide all | Show all
Screenshot_from_2022-12-08_13-28-55.png
Attachment 11: Screenshot_from_2022-12-08_16-49-08.png  837 kB  Uploaded Thu Dec 8 17:16:14 2022  | Hide | Hide all | Show all
Screenshot_from_2022-12-08_16-49-08.png
Attachment 12: Screenshot_from_2022-12-08_16-49-21.png  72 kB  Uploaded Thu Dec 8 17:16:35 2022  | Hide | Hide all | Show all
Screenshot_from_2022-12-08_16-49-21.png
Attachment 13: Screenshot_from_2022-12-08_17-19-01.png  71 kB  Uploaded Thu Dec 8 17:19:22 2022  | Hide | Hide all | Show all
Screenshot_from_2022-12-08_17-19-01.png
Attachment 14: Screenshot_from_2022-12-08_17-32-46.png  72 kB  Uploaded Thu Dec 8 17:33:33 2022  | Hide | Hide all | Show all
Screenshot_from_2022-12-08_17-32-46.png
ELOG V3.1.4-395e101