Message ID: 562     Entry time: Thu Sep 22 00:29:04 2022
 Author: ND, SC, AM, VK, IC, VI 
 Status: Under Process 
 Type: Shift summary 
 Category: Ring | Diag 
 Important:
 Subject: Mesures du 22/09 
 Icon:  

9h demarrage modulateur et schillers

Cyclage aimants

Asservissement laser ON

10h25 : Scan charge phase

11h Reglage linac

LI/ICT.01 50pC avec iris=2mm

12:00 Ligne deviee: Faisceau instable

12:30 Camera timing scan on TL/DG/SST.01 (see attached plot) + Trying to fix trigger issue on TL/DG/SST.02

14:00 Single shot OTR!!!

15:00 Faisceau stable sur TL/DG/SST01 avec steerer ON mais instable sur TL/DG/SST.02

=> Faisceau instable en energie

16:00 Rechargement de la recette du 19/9 a 21h25 => faisceau dans l 'anneau

16:30 Septum voltage 97V

Debut du second tour oberve sur le scintillateur!

Septum optimum timing=-38us

Kicker timing -7.250us (see attached plot: No effect on RI-C1/BPM.02, strong effect on RI-C1/BPM.03, medium effect on RI-C2/BPM.01)

19:00 Arret

Le modulateur n'est pas tombe de la journee.

 

 

 

 

 

 

 

 

 

 

 

 


 

Plan for the beam time

1) Start the llinac

2) Scan in time camera LI/DG/SST.01

3) Re-establish beam transport to ring

4) Scan in time the septum

5) Scan in voltage the septum

6) Adjust timing of kicker by looking at induced noise on ICTs

7) Scan in time the kicker

8) Scan in voltage the kicker

9) Adjust steerers as needed...

Attachment 1: scan_charge_phase.png  40 kB  Uploaded Thu Sep 22 12:18:05 2022  | Show | Hide all | Show all
Attachment 2: camera_delay_scan_m40us.png  46 kB  Uploaded Thu Sep 22 14:33:37 2022  | Hide | Hide all | Show all
camera_delay_scan_m40us.png
Attachment 3: camera_delay_scan_long_delay.png  45 kB  Uploaded Thu Sep 22 15:01:37 2022  | Show | Hide all | Show all
Attachment 4: 2022-09-22_13_58_54_tl_dg_sst_01-ccd_01_log_scale_False_despeckle_False_min_scale_30_max_scale_50.png  400 kB  Uploaded Thu Sep 22 15:02:33 2022  | Hide | Hide all | Show all
2022-09-22_13_58_54_tl_dg_sst_01-ccd_01_log_scale_False_despeckle_False_min_scale_30_max_scale_50.png
Attachment 5: bpm_0_vs_septum.png  114 kB  Uploaded Thu Sep 22 20:06:01 2022  | Hide | Hide all | Show all
bpm_0_vs_septum.png
Attachment 6: bpm_1_vs_septum.png  110 kB  Uploaded Thu Sep 22 20:06:11 2022  | Show | Hide all | Show all
Attachment 7: bpm_2_vs_septum.png  115 kB  Uploaded Thu Sep 22 20:06:21 2022  | Show | Hide all | Show all