Entry   Entered by Super Team from 134.158.195.142 on Wed Feb 16 18:13:48 2022; Mesures journée vacances (VC/HG) 6x
    Reply   Entered by Super Team from 134.158.195.142 on Wed Feb 16 18:13:48 2022; RE: Mesures journée vacances (VC/HG) charge_phase__at_16-02-2022__17-46-08.jpg
Message ID: 345     Entry time: Wed Feb 16 18:14:03 2022     Reply to this: 346
 Author: Entered by Super Team from 134.158.195.142 on Wed Feb 16 18:13:48 2022 
 Status: Under Process 
 Type: Linac 
 Category: Linac Commissionning 
 Important:
 Subject: Mesures journée vacances (VC/HG) 
 Icon:  

 

Mesures portant sur la compréhension de sensibilité de la taille du faisceau mesuré sur SST1 en fonction de la phase RF. 

Ci dessus : plot de trend de la taille du faisceau ainsi que la position. Les variations peu avant 16h10 sont liés à un changement à la main de la phase de quelques degrés (jusqu'à 10). la mesure est sensible au moins au degrés de phase. 

les fluctuations sont dus certainement à la variation de la phase RF. Il faudrait faire une étude plus poussée en corrélant ces données avec les mesures au scope (Vincent) sur le déphasage. 

on voit que le déphasage augmante peu après 16h30. 

Rappel : une fois le laser alligné, le spot du faisceau sur SST1, sans bobine, est focalisé. 

   à la phase de charge max : 103°

 

  à la phase suiante : 104°

 à 105° 

Et si on trace les tailles et positions en fonction de la phase (phase_max +/- 10°)

 

 

Attachment 5: Screenshot_from_2022-02-16_18-31-21.png  125 kB  | Show | Show all