Message ID: 1172     Entry time: Thu Dec 18 09:39:38 2025
 Author: DN, IC, HG, KD, MJ, and Co 
 Status:  
 Type: Shift summary 
 Category: LI | TL | LE | Ring | Diag | Aimants | Laser | Vide | Linac Commissionning | Ring Commissioning 
 Important:
 Subject: X-ray measurement/characterization campaign 
 Icon:  

The machine was warmed up remotemy

The FPC is ready. The laser is locked.

9h Start HV

9h08 Modulator is put to standby. Access to "repair" shutter X-line

9h20 Restart the beam

9h39 Problem with the camera laser photocathode. It does not start. So; feedback does not work and the generated charge is drifting.

9h45 Another access to fix/restart the camera

10h Camera is working. Chillers gun and RF structure are ON also now;

10h30 Beam in the ring
Miss triggering issues, see ICT data for example. 
13h : Kevin recabled the delay box on the "right" cable to avoid bad 50 Hz signal.  

Attachment 1: Q_missed_2025-12-18_13-50-19.png  12 kB  Uploaded Thu Dec 18 13:50:56 2025  | Hide | Hide all
Q_missed_2025-12-18_13-50-19.png