Message ID: 1048     Entry time: Mon Mar 31 09:53:26 2025
 Author: VM, IC, RC 
 Status: Under Process 
 Type: Shift summary 
 Category: Ring Commissioning 
 Important:
 Subject:  
 Icon:  

08h00 ThomX started by Maher

09h50 Problem with vacuum in the septum. TL-V3 and EL-V1 are closed.

ThomX configuration changed to 'Linac'.

0955 Laser is 'On'

10h03 Problem with vacuum was fixed. ThomX configuration changed to 'ThomX'.

10h05 Cycling all magnets

10h10 HV is 'On'

10h20 From time to time TO-V3 and EL-V1 close. Septum vacuum is 2.6e-10

Septum power supply is interlocked

10h55 , RF gun phase is 235 dg., Sect. phase is 216 dg., Att. = 2.38 dB, TL/BPM2 X=0.2 mm , Charges: -91 pC, -90 pC, -98 pC, Linac steerers: H [0.84 -2.88], V [-2.47 2.8], receipt from 20250321 12:30:52

11h27 V6 interlocks

11h49 RF gun phase is 225 dg., Sect. phase is 209 dg., Att. = 2.46 dB, TL/BPM2 X=0.2 mm

12h46 to 13h10 Emittance measurements at 50 MeV

13h Problem with Pulsed Elements => fixed by Kevin and Maher

13h30 Tuning of the linac for 70 MeV, emittance measurements.

14h Check the machine at 50 MeV

15h25 The modulator at standby mode. Access to the bunker.

15h45 61.5 MeV receipt from 14/02/2025

Synchronization problem,

17h00 RCDS on injection

17h19 RF Gun phase is 224 dg., Sect. phase 221 dg. Att. 0.975 dB, Charges: -107 pC, -105 pC, -115 pC. TL/BPM2 X=1 mm, RF cav. 100 kV, phase -34 35 dg. manual phase sfifter 7809, phase shifter to measure amplitude 6759. Receipt 20250331 17:12:34

 

Attachment 1: Screenshot_from_2025-03-31_18-06-59.png  32 kB  Uploaded Mon Mar 31 19:09:04 2025  | Hide | Hide all
Screenshot_from_2025-03-31_18-06-59.png
Attachment 2: Screenshot_from_2025-03-31_17-52-04.png  85 kB  Uploaded Mon Mar 31 19:09:04 2025  | Hide | Hide all
Screenshot_from_2025-03-31_17-52-04.png
Attachment 3: Screenshot_from_2025-03-31_17-14-56.png  693 kB  Uploaded Mon Mar 31 19:09:04 2025  | Hide | Hide all
Screenshot_from_2025-03-31_17-14-56.png
Attachment 4: 2025-03-31_10_40_04_li_dg_sst_01-ccd_01_RAW.png  205 kB  Uploaded Mon Mar 31 19:09:04 2025  | Hide | Hide all
2025-03-31_10_40_04_li_dg_sst_01-ccd_01_RAW.png
ELOG V3.1.4-395e101