14h31 Start ThomX/ Modulator, Frig, Laser
14h37 Cycling all magnets, Chillers started
15h34 HV is 'On'
There are problems with the servers. Therefore, some tools are not working: Trends, Camera Laser and so on.
Servers restarted, we also used script from Kevin to restart properly DSs.
Beam Charge : 70 pC !!! RF gun phase is set to 109 dg.
17h30 Linac steerers H [0.67 -2.77], V [-2.95 3.19], RF Gun phase 214 dg. Att. 2.47 dB.
Measure dispersion in the TL
18h45 QP4 - QP7 set to 0
Screenshots of TL orbit for different Att.
18h53 HV is 'OFF', Stop thomX
|