HOME Prise de donnees MML Controle commande Simulations Notes Hardware Ligne X Laser Interaction Diagnostiques Synchronisation
Commissionning Commissionning Preparation Pannes ShiftCheck
  Toutes les notes concernant les Commissionning de ThomX  Not logged in ThomX    logo
Message ID: 1016     Entry time: Thu Feb 20 08:25:11 2025
 Author: Entered by Super Team from 134.158.195.141 on Thu Feb 20 08:24:55 2025 
 Status: Under Process 
 Type: Shift summary 
 Category: Ring Commissioning 
 Important:
 Subject:  
 Icon:  

08h25 Start ThomX; Start ThomX: Modulator, Fridge, Laser

08h32 Chillers were started, cycling all magnets

11h23 HV is 'On'

11h46 RF Gun Phase is 28 dg. Sect Att. is 2.54 dB, Phase is 209 dg. TL/BPM2 X=0, Charges: -88, -92, -96 pC

Linac correctors: H [0.59 -2.86], V [-3.23 3.47]

12h24 Beam in the ring RF 50 kV, Phase 44 dg.

12h35 RF 150kV, Phase 32 Kicker delay 7.3952 us,  9497 V

17h10 HV on 'Sttandby', the laser gate closed, injection kicker pulse correction

17h52 injection kicker pulse was corrected

HV is 'On'

18h39 The beam is in the ring. It is OK!

18h45 Stop ThomX

Attachment 1: Screenshot_from_2025-02-20_18-42-31.png  120 kB  Uploaded Thu Feb 20 18:43:17 2025  | Hide | Hide all | Show all
Screenshot_from_2025-02-20_18-42-31.png
Attachment 2: Screenshot_from_2025-02-20_18-42-20.png  69 kB  Uploaded Thu Feb 20 18:43:17 2025  | Hide | Hide all | Show all
Screenshot_from_2025-02-20_18-42-20.png
Attachment 3: Screenshot_from_2025-02-20_18-42-05.png  109 kB  Uploaded Thu Feb 20 18:43:17 2025  | Hide | Hide all | Show all
Screenshot_from_2025-02-20_18-42-05.png
Attachment 4: Screenshot_from_2025-02-20_18-41-25.png  21 kB  Uploaded Thu Feb 20 18:43:17 2025  | Show | Hide all | Show all
Attachment 5: Screenshot_from_2025-02-20_18-41-02.png  20 kB  Uploaded Thu Feb 20 18:43:17 2025  | Show | Hide all | Show all
Attachment 6: Screenshot_from_2025-02-20_18-40-47.png  78 kB  Uploaded Thu Feb 20 18:43:17 2025  | Show | Hide all | Show all
ELOG V3.1.4-395e101