Message ID: 1008     Entry time: Tue Feb 11 10:31:57 2025
 Author: ND, Marie Labat 
 Status: Under Process 
 Type: Shift summary 
 Category: Diag 
 Important:
 Subject: Streak camera 
 Icon:  

9:20 Start aligning

12:40 Alignement done for both linac and ring.

Health check: Archiving not working

12:52 Start beam

Pb temperature gun and section

14:00 Beam on Cerenkov

Fixing misc. problems.

One motor of the MRSV mirror is dead.

17:30 Beam length measurement. t~15ps (convoluted with transport and focalisation)

*Note:*

- Time lost due to chiller problems

 

Attachment 1: 20250211_173802.jpg  127 kB  Uploaded Tue Feb 11 22:35:34 2025  | Hide | Hide all
20250211_173802.jpg
Attachment 2: 20250211_174708.jpg  129 kB  Uploaded Tue Feb 11 22:36:02 2025  | Hide | Hide all
20250211_174708.jpg
ELOG V3.1.4-395e101