Message ID: 56     Entry time: Mon Jun 12 09:51:00 2023
 Author: IC, VK, VM, LS, JH, MB, ND 
 Status: New Solution 
 Type: Info 
 Category: Prise de donnees 
 Important:
 Subject: Summary of the ring commissioning meeting 
 Icon:  

Comments:

* There are strong evidences that part of the frequency problem comes from mechanical issue

* Fring field of the dipoles seems to be longer than anticipated. This could lead to shortening of the orbit.

Decisions:

* Have a meeting with mechanics to understand what are the issues and what are the possibilities to address the ring length issue.

* CFP is welcome to operate *remotely* during ring operations. A script will be made to monitor the X-ray flux during operations.

* Wednesday, Thursday and Friday : CFP can access until 11h.

* Investigate the operation of the BLM.

* Tuesday afternoon Nicolas and Sophie will investigate the feedback issue (phase or attenuator to stabilize TL/BPM.02/SpX).

Plan for this week: prepare the beam to test the X-ray production.

 

 