  Status of installation, including shipping and de-installation of test setups.  Not logged in ELOG logo
Entry   Vacuum in the mirror chambers, posted by Manar Amer at ThomX igloo about vacuum | cabling | software First_Level_Pump.jpgSecond_Level_Pump_Turpo_blades_Controlers.jpgInkedControl_Room_Gauge_Monitoring_screen.jpgInkedOptical_cavity_vacuum_control_Modules.jpg
    Reply   Vacuum in the mirror chambers, posted by Manar Amer at ThomX igloo about vacuum | cabling | software 
Message ID: 19     Entry time: Fri Oct 15 14:34:34 2021     In reply to: 18
 Author: Manar Amer 
 Status: Fixed 
 Type: report 
 Category: vacuum | cabling | software 
 Location: ThomX igloo 
 Title: Vacuum in the mirror chambers 

the ionic pumps have been also connected this morning but not powered on, yet.
the vacuum group is waiting for a vacuum level below 10**-6 to power them on.

it should be the case this afternoon.

about permanent cables on the optical table for the vacuum system, there are 2 for the gauges and 1 for the ionic pump for each vessel, then 6 in total.

 

Manar Amer wrote:
  • The electron ring has been vacuum inside it, but the valves connecting it to the two mirror chambers are closed. Before commencing to do measurements on the cavity, we must place the mirrors under the proper vacuum and open the valves connecting them to the electron ring.

 

  • The vacuum system is consistent of three levels; Normal (max ~10^-3 mbar), turbo (max ~ 10^-7 mbar) and ionization.
  • With the help of  Frédéric LETELLIER and Mercier Bruno from the vacuum department in the morning.
    • Installation of the first level vacuum (normal pump)
    • Installation of the second level vacuum (turbo pump)
      • can reach up to 1350 Hz = 81 000 rotation per min (how fast it reaches max rotation depends on how good the first level pump was done)
    • Installation of the connections to the gauge meter, there are two gauges, one for first level and one for second.
  • All turned on !!

 

  • Both are on and can be monitored from ThomX control room
    • The attached photo from the control room shows how we will be able to get a graph of vacuum over time.
      • (we were able to reach approximately for Volume 11 and Volume 12 respectively 4.1*10^-6 and ~8*10^-7)
        • to explain Volume 11 and volume 12 (look at Location of ThomX vacuum valves photo)

 

  • A photo of the control module placed outside the bunker to control the optical cavity vacuum is attached
  • This afternoon the third system will be installed and turned on

*** Note after vacuum is set there will be three permeant cables inside the cavity box for monitoring.

 