Status of commissioning, report also here plots are reports., Page 24 of 24
Not logged in
Find
|
Login
|
Help
Full
| Summary |
Threaded
464 Entries
Goto page
Previous
1
,
2
,
3
...
22
,
23
, 24
All
ID
Date
Author
Status
Type
Category
Location
Title
Text
441
Thu Jul 10 18:02:54 2025
Ronic Chiche
Fixed
info
detectors and electronics
ThomX igloo
laser PZT amplifier
this afternoon, I added the Gain = 2.8
amplifier at the output of the Laselock to
drive the laser PZT.
449
Wed Aug 27 12:01:41 2025
Ronic Chiche
Fixed
info
detectors and electronics
ThomX igloo
Power shut down on August 29th
This morning, all the equipments have been
switched off due to a power shut down
tomorrow morning.
450
Thu Aug 28 18:01:46 2025
Ronic Chiche
Fixed
info
detectors and electronics
ThomX igloo
Power shut down on August 29th
after alignment, CEP adjustment and optimizing
the PDH phase, I got back ~92kW in the FPC
for 33% amplifier ratio.
66
Thu Oct 3 14:00:13 2019
Loïc Amoudry
Fixed
issue
cabling
Optical room
Electrical trouble (disjunction)
The circuit breaker on ThomX cavity drops
@1.5-1.8kW when we turn on 1/2nd
stage of the amplifier or 3rd stage of the