  271   Mon Oct 9 13:11:23 2023 Daniele NutarelliFixedinfolasers and opticsThomX iglooTests of pointing stability of the laser CFP

Last monday with Victor we have cheked the stability of de pointing of the laser FP.

The climatisation was operating since 3 days in satble way. The laser pointing was very stable before to inejct in to the cavity (picture 1) and also for the reflexion from the cavity (picture 2).

That means thant it is necessary to have a stable climatisation operation.

Attachment 1: IMG_20231003_155009_resized_20231009_103610100.jpg
IMG_20231003_155009_resized_20231009_103610100.jpg
Attachment 2: IMG_20231003_155458_resized_20231009_103610449.jpg
IMG_20231003_155458_resized_20231009_103610449.jpg