HOME
SBOX
THOMX
MINICAV
Utilities
THOMX orders
THOMX installation
THOMX commissioning
THOMX control command
Status of commissioning, report also here plots are reports., Page 24 of 24
Not logged in
Find
|
Login
|
Help
Full
| Summary |
Threaded
463 Entries
Goto page
Previous
1
,
2
,
3
...
22
,
23
, 24
All
ID
Date
Author
Status
Type
Category
Location
Title
Text
449
Wed Aug 27 12:01:41 2025
Ronic Chiche
Fixed
info
detectors and electronics
ThomX igloo
Power shut down on August 29th
This morning, all the equipments have been
switched off due to a power shut down
tomorrow morning.
450
Thu Aug 28 18:01:46 2025
Ronic Chiche
Fixed
info
detectors and electronics
ThomX igloo
Power shut down on August 29th
after alignment, CEP adjustment and optimizing
the PDH phase, I got back ~92kW in the FPC
for 33% amplifier ratio.
66
Thu Oct 3 14:00:13 2019
Loïc Amoudry
Fixed
issue
cabling
Optical room
Electrical trouble (disjunction)
The circuit breaker on ThomX cavity drops
@1.5-1.8kW when we turn on 1/2nd
stage of the amplifier or 3rd stage of the
Goto page
Previous
1
,
2
,
3
...
22
,
23
, 24
All
ELOG V3.1.4-395e101