Status of commissioning, report also here plots are reports., Page 24 of 24
Not logged in
Find
|
Login
|
Help
Full
| Summary |
Threaded
463 Entries
Goto page
Previous
1
,
2
,
3
...
22
,
23
, 24
All
ID
Date
Author
Status
Type
Category
Location
Title
Text
462
Wed Dec 3 16:23:40 2025
Ronic Chiche
Fixed
report
lasers and optics | detectors and electronics
ThomX igloo
Noise issue
yesterday, in the same conditions, we had
so many locking issues... exactly
in the same way than before. :-(
463
Mon Dec 8 11:17:17 2025
Ronic Chiche
Fixed
issue
lasers and optics | detectors and electronics
ThomX igloo
High frequency noise
This morning, I installed a high-voltage
probe (1:1000) on the AC-line to see if one
could detect a correlation between lock losses
464
Mon Feb 2 15:29:45 2026
Ronic Chiche
Fixed
info
lasers and optics
ThomX igloo
Laser Amplifier used at 70%
today, I installed a laser dump just before
the telescope to avoid any high power (50W
instead of 17W usually) issue in the injection