  Status of commissioning, report also here plots are reports.  Not logged in ELOG logo
Message ID: 68     Entry time: Wed Oct 9 10:08:24 2019
 Author: Loïc Amoudry 
 Status: Fixed 
 Type: info 
 Category: lasers and optics 
 Location: Optical room 
 Title: Improvement holder amplifier fiber 

We've added a clamp in the 3rd stage to prevent the pump fiber from moving and tilting (it was tilting to the left).