Message ID: 447     Entry time: Fri Jul 18 15:56:40 2025
 Author: Ronic Chiche 
 Status: Under Process 
 Type: info 
 Category: lasers and optics 
 Location: ThomX igloo 
 Title: laser operation again with machine OFF 

The laser start at 33% with 92 KW optimized and

P=0.03

I=0.0005

I2=0

D=0.5

But we have more and more problems with the alignement from a day to another!!!

We start the machine and we do Xrays again.

The lock is easy and stable, we see some hig fraq perturbations but no delock as yesterday.

ATTENTION!!!!! when one switch ON or OFF the hexapode motors we have big delock like what we observed some time during the operation!!!!!

For the big delock we have to investigate the operation of the hexapode!!

We have changed the orbit and obtained almost 40000 Xrays. with an ebeam dimension of 121 µm rms.

And now I go in Hollydays!!

See you after 15 august

Daniele