Message ID: 236     Entry time: Tue Sep 5 18:21:12 2023
 Author: Ronic Chiche 
 Status: Fixed 
 Type: info 
 Category: lasers and optics 
 Location: ThomX igloo 
 Title: FP-cavity FSR shift 

today, to match the ring frequency at 500.25MHz (15th laser harmonic), we did a frequency shift on the laser using the Smaract motors (not too fast, ~2µm/s, to prevent laser modelock loss)
and we "followed" this shift on the FP-cavity using the FP-cavity motors.

we did several steps during the operation, to control the alignment, coupling and transmission.

finally, we locked again the laser and FP-cavity at 17kW for 30% of input power.
the coupling was quite low ~10%

Attachment 1: 20230905_173506.jpg  181 kB  | Show | Show all