Entry   Dust Cleaning of SBox, posted by Manar Amer at Optical room about utilities Log_Top_window.jpgLog_Reflection_window.jpgLog_Injection_Side_window.jpgLog_Injection_side_window2.jpg
    Reply   Dust Cleaning of SBox, posted by Manar Amer at Optical room about utilities 
       Reply   Dust Cleaning of SBox, posted by Manar Amer at Optical room about mechanics | lasers and optics | utilities 6x
          Reply   Dust Cleaning of SBox, posted by Manar Amer at Optical room about mechanics | lasers and optics | utilities 20220331_Dust_Meter_Outside_cavity_Av10min.jpg20220331_Dust_Meter_Inside_cavity_Av10min.jpg
Message ID: 68     Entry time: Wed Mar 23 18:17:45 2022     In reply to: 67     Reply to this: 71
 Author: Manar Amer 
 Status: Fixed 
 Type: report 
 Category: utilities 
 Location: Optical room 
 Title: Dust Cleaning of SBox 

The cleaning was done twice with half an hour interval between the two times
reading on the dust meter was taken after each time, and it was zero averaged over a 10-min

Manar Amer wrote:

An Initial cleaning of the KBoX outside was done, All the optics and mechanics placed that were on the table were removed.

Only the old Mitylaser amplifier remains on the table.

Since we will be using the ThomX Celia amplifier, we will remove it and place it in a secure location (to be decided).

Tomorrow a cleaning of the inside of the cavity box is to be done.

 