Message ID: 31     Entry time: Tue Oct 5 16:23:04 2021
 Author: Aurélien Martens 
 Status: Fixed 
 Type: report 
 Category: detectors and electronics | software 
 Location: Optical room 
 Title: new position of smaract motors 

after 3hours (1pm --> 4pm) the cavity moved by 12um in total

new positions: +5.1065mm on M1 and M2 (5.1050 before)

the drift is 4um/hour which amounts to about 10kHz drift / hour+the temperature of the optics room also changed unfortunaltey (linked to extinction of air flow at around 11am this morning). the drift in the room temperature was about 0.5K from 1pm to 2pm and 3K since 11am.

maybe this measurement needs to be redone to more precisely correlate the drift to an overall temperature change